In remedy cases, record-keeping and oversight activities by the Contracting
Officer's Representative are of fundamental importance for further government
response. The COR is of value because it:
All of the above apply (Documenting, Communicating, Monitoring)
If a contractor is in default of part of the contract and that part is severable from
the remainder of the contract that will continue, then the Contracting Officer
can use a Partial Termination of the deficient part of the contract.
True
The Contracting Officer's Representative is responsible for safeguarding all
proprietary data
True
The critical thing that formal communication differs from is that formal
communication that is binding upon the parties, whereas informal
communication is non-binding.
True
The COR is responsible for communications with the _______.
Contracting Officer, Functional Supervisor and the Contractor
, CLC 222 MODULE 3
When providing technical direction to the contractor, the Contracting Officer's
Representative must be mindful not to issue Improper Technical Direction and
must make a choice from which of the following?
Fail to act if performance is late or inadequate.
The reason the COR needs to understand the contract and how it is organized is
so that he understands all requirements and deliverables of the contract. This
will allow the COR to track contractor performance and monitor the contractor
for compliance with the contract as written.
True
The COR has identified that a change to the contract will increase cost. What
must occur for the contracting officer to modify the contract.
Identify the change to the contract, complete a technical evaluation of the
contractor's proposal, develop the estimated cost, obtain the required approvals,
and obtain funding
The COR should work with the Contracting Officer if the COR identifies a need
to change the current contract.
True
An Accounting Classification Requirement Number (ACRN) is:
Always a two-digit alpha code
Officer's Representative are of fundamental importance for further government
response. The COR is of value because it:
All of the above apply (Documenting, Communicating, Monitoring)
If a contractor is in default of part of the contract and that part is severable from
the remainder of the contract that will continue, then the Contracting Officer
can use a Partial Termination of the deficient part of the contract.
True
The Contracting Officer's Representative is responsible for safeguarding all
proprietary data
True
The critical thing that formal communication differs from is that formal
communication that is binding upon the parties, whereas informal
communication is non-binding.
True
The COR is responsible for communications with the _______.
Contracting Officer, Functional Supervisor and the Contractor
, CLC 222 MODULE 3
When providing technical direction to the contractor, the Contracting Officer's
Representative must be mindful not to issue Improper Technical Direction and
must make a choice from which of the following?
Fail to act if performance is late or inadequate.
The reason the COR needs to understand the contract and how it is organized is
so that he understands all requirements and deliverables of the contract. This
will allow the COR to track contractor performance and monitor the contractor
for compliance with the contract as written.
True
The COR has identified that a change to the contract will increase cost. What
must occur for the contracting officer to modify the contract.
Identify the change to the contract, complete a technical evaluation of the
contractor's proposal, develop the estimated cost, obtain the required approvals,
and obtain funding
The COR should work with the Contracting Officer if the COR identifies a need
to change the current contract.
True
An Accounting Classification Requirement Number (ACRN) is:
Always a two-digit alpha code