236
ANSWER ALL QUESTIONS IN THIS SECTION
QUESTION 1
What two things are designated on a certificate to operate from the Chief Boiler
Inspector? - ANSWERS-1. Inspection Date
2. MAWP
QUESTION 2
Where are funds held collected from inspections? - ANSWERS-Trust and agency
fund
QUESTION 3
How long do you have to file a grievance with the department for an administrative
hearing? - ANSWERS-15 days
END OF
PAGE 1
,KENTUCKY BOILER EXAM KRS 2024
236
QUESTION 4
Where is the petition filed for a grievance with the Department? - ANSWERS-
Franklin Circuit Court
QUESTION 5
Do you need a contractor's license to erect boilers? - ANSWERS-Yes
QUESTION 6
How often do contractor's need to renew their licenses' for construction? -
ANSWERS-Annually * First of the month following expiration
QUESTION 7
Upon suspension or revocation of a license, how long does the Department have to
provide notice? - ANSWERS-Written notice must be provided within 10 Days
END OF
PAGE 2
, KENTUCKY BOILER EXAM KRS 2024
236
QUESTION 7
What is the cost for a replacement license? - ANSWERS-$5
QUESTION 8
What do permit fees for installation / erection / repair of boilers or pressure vessels
include? - ANSWERS-Initial / Final Inspection
QUESTION 9
During an emergency, how long do owner / operators have until permits must be
submitted to the Department? - ANSWERS-30 Days to file
QUESTION 10
Do Department inspectors need to call ahead before an inspection? - ANSWERS-
No
END OF
PAGE 3