ICC Service Technician Study Guide
Questions & Answers
According to CCR, Title 23 UST Regulations, What is the frequency that the
Monitor Certification must be performed? - -Every 12 Months
-If visual monitoring is utilized as the means of release detection for single
walled tank, it must be conducted on a _______ Basis. - -Daily
-The Purpose of spill and overfill protection equipment is to minimize the
potential for a release during: - -Fuel Deliveries
-Which of the following is a potential symptom of toxic petroleum exposure: -
-Dizziness
Tremors
Eye irritation
All of the above(correct)
-Under-Dispenser Containment is required for ______ underground storage
tank systems - -All
-All of the following are true for Automatic Tank Gauging (ATG) except for: - -
ATG system are required to be installed in all UST system
-According to CCR Title 23, UST regulations Spill containment (spill bucket)
must meet all of the following requirements except: - -Be installed on vent
risers
-Suction piping may not require leak detection if it has one check valve
located where? - -Directly below the suction pump
-Service Technician performing work on Monitoring equipment must be
trained and certified by __________ - -The manufacture of the equipment.
-Air monitoring must be conducted ________ when performing work within a
confined space. - -Prior to and during
-A UST Service Technician must be recertified by the equipment Manufacture
at the time interval recommended by the equipment manufacture or at least
every ____ months, whichever is greater. - -36 Months
-When an automatic tank gauge is utilized for single-walled tank leak
detection, it shall test the tank at least monthly after product delivery or
, when the tank is filled to within _____ percent of the highest operating level
during the previous month. - -10
-The following is true of spill buckets except: - -Must provide drainage for
spilled product into the secondary containment sump.
-If during an inspection of dispensing equipment at a retail gas station you
find that the product is dispensing at a significant lower rate than usual. You
should check: - -For piping leaks.
-According to CCR title 23, UST Regulations the local agency must be notified
by the Owner/Operator how long before conducting Secondary Containment
Testing? - -At least 48 hours before the test.
-Poppet Valves are a Vapor Recovery Component installed: - -on the vapor
recovery riser
-If equipped with an ATG it shall be programmed to test the tank _______? - -
at least monthly
-A Vacuum-assist nozzle is a component of a(n) ________? - -Stage II vapor
recovery system
-Stage I Vapor Recovery can be installed in the following configured(s): - -
Dual Point, Manifold, & Coaxial
-An Underground tank System includes: - -The underground storage tank
Piping
Ancillary Equipment
All of the above is correct
-If equipped with an overfill alarm, the alarm must be triggered to alert the
delivery operator when the tank is no more than _______ full. - -90%
-Approved Cathodic Protection Methodologies include: - -Sacrificial Anodes, &
Impressed current system
-_________is a system for exchanging gasoline vapors in a storage tank(s) and
product in a fuel delivery truck. - -Stage I Recovery
-Automatic Line Leak Detectors, installed on Underground Piping with
Secondary Containment. Shall be capable of detecting a leak of _______ at 10
PSI. - -3 gallons per hour (GPH)
-The fastest exposure for Petroleum Toxicity to affect the body is through: - -
Inhalation (Through breathing)
Questions & Answers
According to CCR, Title 23 UST Regulations, What is the frequency that the
Monitor Certification must be performed? - -Every 12 Months
-If visual monitoring is utilized as the means of release detection for single
walled tank, it must be conducted on a _______ Basis. - -Daily
-The Purpose of spill and overfill protection equipment is to minimize the
potential for a release during: - -Fuel Deliveries
-Which of the following is a potential symptom of toxic petroleum exposure: -
-Dizziness
Tremors
Eye irritation
All of the above(correct)
-Under-Dispenser Containment is required for ______ underground storage
tank systems - -All
-All of the following are true for Automatic Tank Gauging (ATG) except for: - -
ATG system are required to be installed in all UST system
-According to CCR Title 23, UST regulations Spill containment (spill bucket)
must meet all of the following requirements except: - -Be installed on vent
risers
-Suction piping may not require leak detection if it has one check valve
located where? - -Directly below the suction pump
-Service Technician performing work on Monitoring equipment must be
trained and certified by __________ - -The manufacture of the equipment.
-Air monitoring must be conducted ________ when performing work within a
confined space. - -Prior to and during
-A UST Service Technician must be recertified by the equipment Manufacture
at the time interval recommended by the equipment manufacture or at least
every ____ months, whichever is greater. - -36 Months
-When an automatic tank gauge is utilized for single-walled tank leak
detection, it shall test the tank at least monthly after product delivery or
, when the tank is filled to within _____ percent of the highest operating level
during the previous month. - -10
-The following is true of spill buckets except: - -Must provide drainage for
spilled product into the secondary containment sump.
-If during an inspection of dispensing equipment at a retail gas station you
find that the product is dispensing at a significant lower rate than usual. You
should check: - -For piping leaks.
-According to CCR title 23, UST Regulations the local agency must be notified
by the Owner/Operator how long before conducting Secondary Containment
Testing? - -At least 48 hours before the test.
-Poppet Valves are a Vapor Recovery Component installed: - -on the vapor
recovery riser
-If equipped with an ATG it shall be programmed to test the tank _______? - -
at least monthly
-A Vacuum-assist nozzle is a component of a(n) ________? - -Stage II vapor
recovery system
-Stage I Vapor Recovery can be installed in the following configured(s): - -
Dual Point, Manifold, & Coaxial
-An Underground tank System includes: - -The underground storage tank
Piping
Ancillary Equipment
All of the above is correct
-If equipped with an overfill alarm, the alarm must be triggered to alert the
delivery operator when the tank is no more than _______ full. - -90%
-Approved Cathodic Protection Methodologies include: - -Sacrificial Anodes, &
Impressed current system
-_________is a system for exchanging gasoline vapors in a storage tank(s) and
product in a fuel delivery truck. - -Stage I Recovery
-Automatic Line Leak Detectors, installed on Underground Piping with
Secondary Containment. Shall be capable of detecting a leak of _______ at 10
PSI. - -3 gallons per hour (GPH)
-The fastest exposure for Petroleum Toxicity to affect the body is through: - -
Inhalation (Through breathing)