100% satisfaction guarantee Immediately available after payment Both online and in PDF No strings attached 4.2 TrustPilot
logo-home
Exam (elaborations)

OMIS 635 Test 2 Question and answers already passed

Rating
-
Sold
-
Pages
36
Grade
A+
Uploaded on
06-11-2024
Written in
2024/2025

OMIS 635 Test 2 Question and answers already passed OMIS 635 Test 2 What is resource smoothing (or leveling)? - correct answer Involves attempting to even out varying demands on resources by using slack (delaying noncritical activities) to manage resource utilization when resources are adequate over the life of the project What is resource-constrained scheduling? - correct answer The duration of a project may be increased by delaying the late start of some of its activities if resources are not adequate to meet peak demands What are technical or logic constraints? - correct answer Constraints related to the networked sequence in which project activities must occur What are physical constraints? - correct answer Activities that cannot occur in parallel or are affected by contractual or environmental conditions What are resource constraints? - correct answer The absence, shortage, or unique interrelationship and interaction characteristics of resources that require a particular sequencing of project activities People, materials, equipment What are the types of project constraints? - correct answer -Technical or logic -Physical -Resource

Show more Read less
Institution
OMIS
Course
OMIS











Whoops! We can’t load your doc right now. Try again or contact support.

Written for

Institution
OMIS
Course
OMIS

Document information

Uploaded on
November 6, 2024
Number of pages
36
Written in
2024/2025
Type
Exam (elaborations)
Contains
Questions & answers

Subjects

Content preview

OMIS 635 Test 2
What is resource smoothing (or leveling)? - correct answer ✔Involves
attempting to even out varying demands
on resources by using slack (delaying noncritical activities) to manage
resource utilization when resources are adequate over the life of the project


What is resource-constrained scheduling? - correct answer ✔The duration of
a project may be increased by delaying the late start of some of its activities if
resources are not adequate to meet peak demands


What are technical or logic constraints? - correct answer ✔Constraints
related to the networked sequence in which project activities must occur


What are physical constraints? - correct answer ✔Activities that cannot occur
in parallel or are affected by contractual or environmental conditions


What are resource constraints? - correct answer ✔The absence, shortage,
or unique interrelationship and interaction characteristics of resources that
require a particular sequencing of project activities
People, materials, equipment


What are the types of project constraints? - correct answer ✔-Technical or
logic
-Physical
-Resource


How do you determine the classification of a problem? - correct answer
✔Using a priority matrix will help determine if the project is time or resource
constrained.

,What is a time-constrained project? - correct answer ✔-Must be completed
by an imposed date


-Require use of leveling techniques that focus
on balancing or smoothing resource demands.


-Use positive slack (delaying noncritical activities) to manage resource
utilization over the duration
of the project.


-Time is fixed, resources are flexible: additional resources are required to
ensure project meets schedule.


What is resource-constrained project? - correct answer ✔-Is one in which the
level of resources available cannot be exceeded.
-Resources are fixed, time is flexible: inadequate resources
will delay the project.


What are limiting assumptions? - correct answer ✔-Splitting activities is not
allowed—once an activity is start, it is carried to completion


-Level of resources used for an activity cannot be changed


What are risk assumptions? - correct answer ✔-Activities with the most slack
pose the least risk.


-Reduction of flexibility does not increase risk.

,-The nature of an activity (easy, complex) doesn't increase risk


What are the advantages of resource demand leveling techniques for time-
constrained projects? - correct answer ✔-Peak resource demands are
reduced


-Resources over the life of the project are reduced


-Fluctuation in resource demand is minimized.


What are the disadvantages of resource demand leveling techniques for time-
constrained projects? - correct answer ✔-Loss of flexibility that occurs from
reducing slack


-Increases in the criticality of all activities


What are the order of heuristics
(rules-of-thumb)? - correct answer ✔1) Minimum slack


2) Smallest (least) duration


3) Lowest activity identification number


What is an EMR project? - correct answer ✔The development of a handheld
electronic medical reference guide to be used by emergency medical
technicians and paramedics

, What is the problem with EMR projects? - correct answer ✔There are only
eight design engineers who can be assigned to the project due to a shortage
of design engineers and commitments to other projects.


What are the impacts of resource-constrained scheduling? - correct answer
✔-Reduces slack; reduces flexibility
-Increases criticality of events
-Increases scheduling complexity
-May make the traditional critical path no longer meaningful
-Can break sequence of events
-May cause parallel activities to become sequential
-Activities with slack may become critical


What is splitting? - correct answer ✔-A scheduling technique for creating a
better project schedule and/or increase resource utilization


-Involves interrupting work on an activity to employ the resource on another
activity, then returning the resource to finish the interrupted work.
-Is feasible when startup and shutdown costs are low.
-Is considered the major reason why projects fail to meet schedule.


What are the benefits of scheduling resources? - correct answer ✔-Leaves
time for consideration of reasonable alternatives:
-Cost-time tradeoffs
-Changes in priorities


-Provides information for time-phased work package budgets to assess:
-Impact of unforeseen events

Get to know the seller

Seller avatar
Reputation scores are based on the amount of documents a seller has sold for a fee and the reviews they have received for those documents. There are three levels: Bronze, Silver and Gold. The better the reputation, the more your can rely on the quality of the sellers work.
Academia199 Chamberlain College Of Nursing
View profile
Follow You need to be logged in order to follow users or courses
Sold
351
Member since
3 year
Number of followers
208
Documents
19011
Last sold
16 hours ago

3.9

50 reviews

5
27
4
6
3
7
2
3
1
7

Recently viewed by you

Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their tests and reviewed by others who've used these notes.

Didn't get what you expected? Choose another document

No worries! You can instantly pick a different document that better fits what you're looking for.

Pay as you like, start learning right away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and aced it. It really can be that simple.”

Alisha Student

Frequently asked questions