QUESTIONS & ANSWERS
A Subcontractor's employee incorrectly performs the Work. Who is responsible (to the Owner) for the
error?
1- Subcontractor employee
2- Architect
3- Subcontractor
4- Contractor - ANSWER A201: 3.3.2
Article 3) Contractor
3.3 Supervision and Construction Procedures
4- Contractor
Which of the following is NOT a cause for the Owner to terminate the Contract?
1- The Contractor experiences delays due to a Stop Work order through an act of government
2- The Contractor fails to make payment to Subcontractors for labor
3- The Contractor is guilty of substantial breach of a provision of the Contract Documents
4- The Contractor repeatedly fails to supply enough properly skilled workers - ANSWER A201: 14.2.1
Article 14) Termination or Suspension of the Contract
14.2 Termination by the Owner for Cause
, 1- The Contractor experiences delays due to a Stop Work order through an act of government
Which of the following is owner of all drawings and specifications?
1- Contractor
2- Owner
3- Architect
4- Supplier - ANSWER A201: 1.5.1
Article 1) General Provisions
1.5 Ownership and Use of Drawings, Specifications and Other Instruments of Service
3- Architect
Except for those Claims excluded by this AIA A201 Section 15,2,1, an initial decision shall be required as a
condition precedent to mediation of any Claim arising prior to the date final payment is due, unless 30
days have passed after the Claim has been referred to the Initial Decision Maker with no decision having
been rendered.
1- 10
2- 20
3- 15
4- 30 - ANSWER A201: 15.2.1
Article 15) Claims and Disputes
15.2 Initial Decision
, 4- 30
The ____________ will on request furnish to a ____________ information regarding percentages of
completion or amounts applied for by the Contractor
1- Subcontractor; Owner
2- Architect; Subcontractor
3- Owner; Subcontractor
4- Owner; Architect - ANSWER A201: 9.6.3
Article 9) Payments and Completiong
9.6 Progress Payments
2- Architect; Subcontractor
To whom is the Subcontractor bound to by the Contract Documents?
1- Architect
2- Owner
3- Themselves
4- Contractor - ANSWER A201: 5.3
, Article 5) Subcontractors
5.3 Subcontractual Relations
4- Contractor
The Initial Decision Maker will review claims within 10 days of the receipt of the Claim take one or more
of the following actions. Which of the following actions will NOT be taken?
1- Approve the Claim
2- Request additional supporting data from the Claimant
3- Reject the Claim
4- Ignore the request - ANSWER A201: 15.2.2
Article 15) Claims and Disputes
15.2 Initial Decision
4- Ignore the request
A Sub-subcontractor is a person or entity who has a direct or indirect contract with a/an
________________ to perform a portion of the Work at the site
1- Contractor
2- Subcontractor