kickoff meeting - Correct Answer ✅A meeting has just been
conducted on a project where the expectations, goals, and
objectives of the project have been explained, including the
milestones and timelines of the project. Project sign-off is also
likely to occur during this meeting. What type of meeting was
this?
Responsible, Accountable, Consulted, Informed - Correct Answer
✅What does RACI stand for?
When breaking down project deliverables, what is the lowest level
that is recorded in a WBS? - Correct Answer ✅Work Package
EV for a project is 800, and AC is 1200. CPI for the project would
be which of the following? - Correct Answer ✅.667
The product owner writes them, requirements are known as user
stories - Correct Answer ✅Requirements are known as which of
the following when using a Scrum methodology, and who is
responsible for writing them and prioritizing them?