How many subcontractors and sub-subcontractors are there typically? - ANSWER 10-50
What is crucial about subcontractor coordination? - ANSWER The scope of services
What are a necessary requirement for communication? - ANSWER Meetings
What are important steps when concerning deliveries? - ANSWER You must avoid long periods of of on
site storage; you must verify the load before offloading; and the merch should be checked by the on-site
representative
Productivity - ANSWER This is important because the estimate given to the owner was calculated with
job efficiency in mind.
How does a construction manager play a role in productivity? - ANSWER He must keep a cose watch on
productivity and do everything posible to optimize the conditions that contribute to enhanced
productivity.
What are some factors that can negatively effect the flow of work? - ANSWER Crowded work spaces;
poor coordination of work activities; poor supervision or lack of supervision; inexperience or poorly
trained workforce; not having the proper tools and equipment; inefficient job layout.
How fast do building inspectors usually try to respond? - ANSWER Within a few days of a request for
their services.
Who has the writer had to wait extensive time lengths for when concerning inspections? - ANSWER He
has had to wait weeks and even months on a project waiting for a public utility to respond an inspection
request, authorization, or approval.