SWPPP Study Guide Questions With Real
Answers 2024
Law .set .into .place .in .1970 .for .storm .water .regulation .- .correct .answer.Clean .Water .Act
Regulations .for .monitoring .storm .water .activity .on .a .construction .site, .are .outlined .in .-
.correct .answer.NPDES
When .should .you .read .and .understand .SWPP .- .correct .answer.Immediately .after .project
.is .awarded .and .before .you .begin .any .site .work
What .is .not .an .allowable .storm .water .discharge .or .non-storm .water .discharge .- .correct
.answer.Contaminated .ground .water
When .may .construction .activity .begin .- .correct .answer.When .jurisdiction .of .operations
.specifies .you .can .start
Waters .that .fail .anti-degradation .list .are .placed .on .which .list. .- .correct .answer.303D .list
SWPPPs .certification .are .signed .by .who .- .correct .answer.An .officer .and .project .owner
The .document .that .must .be .completed .signed .and .submitted .to .the .state .to .obtain
.authorization .to .discharge .is .the .NOT. .(T/F) .- .correct .answer.FALSE
NOT .can .be .filed .when .- .correct .answer.All .construction .has .been .completed .both .inside
.and .outside
Operations .on .a .construction .site .are .the .entity .in .charge .of .plans .and .specification .and
.the .entity .who? .- .correct .answer.is .in .charge .of .daily .activities
Motives .for .staying .in .compliance .with .storm .water .objectives? .- .correct .answer.Stay .out
.of .trouble .with .the .law
Objectives .of .the .clean .water .act .are .- .correct .answer.To .protect .and .preserve .beneficial
.use .of .U.S. .waters, .maintaining .their .clean, .physical .and .biological .integrity
NPDES .stands .for .- .correct .answer.National .Pollutant .Discharge .Elimination .System
, Which .are .a .component .of .a .good .SWPPP .- .correct .answer.Site .description .and .maps,
.inspection .and .maintenance .procedure. .Potential .pollutant .sources, .schedules .of
.activities, .site .contact .information, .plan .certification .documents, .site .contact .info .and
.descriptions .of .controls .BMP
Construction .sediment .is .not .considered .a .potential .pollutant .source .(T/F) .- .correct
.answer.False
When .modifying .or .substituting .a .storm .water .BMP .the .contractor .must .consult .with .-
.correct .answer.Project .owner, .SWPPP .designer
NOI .must .be .submitted .to .the .appropriate .agency .before .the .storm .water .pollution
.preventive .plan .is .developed .(T/F) .- .correct .answer.False
Name .of .the .list .with .impaired .waters .is .called .totally .daily .maximum .load .(T/F) .- .correct
.answer.False, .303d .List
You .should .have .a .SWPPP .for .your .construction .site .because? .- .correct .answer.It .is
.required .by .law, .it .documents .storm .water .management .activity .on .your .site, .and .it
.demonstrates .your .intent .to .manage .storm .water .on .your .site
A .well .constructed .SWPPP .for .your .site .should .be? .- .correct .answer.Site .specific
The .NOI .must .be .submitted .when? .- .correct .answer.Prior .to .commencing .construction
One .necessary .component .of .a .good .SWPPP .is? .- .correct .answer.Schedule .of .activities
Factors .that .may .impact .SWPPP .scheduling .activities .include .- .correct .answer.Weather
.and .Climate
Pollutant .sources .on .a .construction .may .include .- .correct .answer.masonry .materials,
.petroleum .storage .tanks, .soil .amendments .fertilizer, .lime .etc
If .you .believe .BMP .modification .are .necessary .to .the .site .you .must? .- .correct
.answer.Seek .written .approval .of .the .project .SWPPP .designer .or .project .owner
The .following .consideration .may .be .incorporated .into .the .SWPPP? .- .correct
.answer.Endangered .species .and .historical .preservation
The .SWPPP .will .contain .the .following? .- .correct .answer.Site .maps, .erosion .sediment
.control, .BMPs, .site .specific .sequences .of .construction .activities
Once .the .site .has .experienced .rain .event .of .measurable .quantity .you .must? .- .correct
.answer.Identify .deficient .and .failed .BMPs .and .make .repairs .immediately
Answers 2024
Law .set .into .place .in .1970 .for .storm .water .regulation .- .correct .answer.Clean .Water .Act
Regulations .for .monitoring .storm .water .activity .on .a .construction .site, .are .outlined .in .-
.correct .answer.NPDES
When .should .you .read .and .understand .SWPP .- .correct .answer.Immediately .after .project
.is .awarded .and .before .you .begin .any .site .work
What .is .not .an .allowable .storm .water .discharge .or .non-storm .water .discharge .- .correct
.answer.Contaminated .ground .water
When .may .construction .activity .begin .- .correct .answer.When .jurisdiction .of .operations
.specifies .you .can .start
Waters .that .fail .anti-degradation .list .are .placed .on .which .list. .- .correct .answer.303D .list
SWPPPs .certification .are .signed .by .who .- .correct .answer.An .officer .and .project .owner
The .document .that .must .be .completed .signed .and .submitted .to .the .state .to .obtain
.authorization .to .discharge .is .the .NOT. .(T/F) .- .correct .answer.FALSE
NOT .can .be .filed .when .- .correct .answer.All .construction .has .been .completed .both .inside
.and .outside
Operations .on .a .construction .site .are .the .entity .in .charge .of .plans .and .specification .and
.the .entity .who? .- .correct .answer.is .in .charge .of .daily .activities
Motives .for .staying .in .compliance .with .storm .water .objectives? .- .correct .answer.Stay .out
.of .trouble .with .the .law
Objectives .of .the .clean .water .act .are .- .correct .answer.To .protect .and .preserve .beneficial
.use .of .U.S. .waters, .maintaining .their .clean, .physical .and .biological .integrity
NPDES .stands .for .- .correct .answer.National .Pollutant .Discharge .Elimination .System
, Which .are .a .component .of .a .good .SWPPP .- .correct .answer.Site .description .and .maps,
.inspection .and .maintenance .procedure. .Potential .pollutant .sources, .schedules .of
.activities, .site .contact .information, .plan .certification .documents, .site .contact .info .and
.descriptions .of .controls .BMP
Construction .sediment .is .not .considered .a .potential .pollutant .source .(T/F) .- .correct
.answer.False
When .modifying .or .substituting .a .storm .water .BMP .the .contractor .must .consult .with .-
.correct .answer.Project .owner, .SWPPP .designer
NOI .must .be .submitted .to .the .appropriate .agency .before .the .storm .water .pollution
.preventive .plan .is .developed .(T/F) .- .correct .answer.False
Name .of .the .list .with .impaired .waters .is .called .totally .daily .maximum .load .(T/F) .- .correct
.answer.False, .303d .List
You .should .have .a .SWPPP .for .your .construction .site .because? .- .correct .answer.It .is
.required .by .law, .it .documents .storm .water .management .activity .on .your .site, .and .it
.demonstrates .your .intent .to .manage .storm .water .on .your .site
A .well .constructed .SWPPP .for .your .site .should .be? .- .correct .answer.Site .specific
The .NOI .must .be .submitted .when? .- .correct .answer.Prior .to .commencing .construction
One .necessary .component .of .a .good .SWPPP .is? .- .correct .answer.Schedule .of .activities
Factors .that .may .impact .SWPPP .scheduling .activities .include .- .correct .answer.Weather
.and .Climate
Pollutant .sources .on .a .construction .may .include .- .correct .answer.masonry .materials,
.petroleum .storage .tanks, .soil .amendments .fertilizer, .lime .etc
If .you .believe .BMP .modification .are .necessary .to .the .site .you .must? .- .correct
.answer.Seek .written .approval .of .the .project .SWPPP .designer .or .project .owner
The .following .consideration .may .be .incorporated .into .the .SWPPP? .- .correct
.answer.Endangered .species .and .historical .preservation
The .SWPPP .will .contain .the .following? .- .correct .answer.Site .maps, .erosion .sediment
.control, .BMPs, .site .specific .sequences .of .construction .activities
Once .the .site .has .experienced .rain .event .of .measurable .quantity .you .must? .- .correct
.answer.Identify .deficient .and .failed .BMPs .and .make .repairs .immediately