100% satisfaction guarantee Immediately available after payment Both online and in PDF No strings attached 4.2 TrustPilot
logo-home
Exam (elaborations)

ARE Project Management - PJM - NCARB Practice Exam Questions And 100% Correct Answers

Rating
-
Sold
-
Pages
8
Grade
A+
Uploaded on
13-10-2024
Written in
2024/2025

ARE Project Management - PJM - NCARB Practice Exam Questions And 100% Correct Answers...

Institution
ARE Project Management - PJM - NCARB
Course
ARE Project Management - PJM - NCARB









Whoops! We can’t load your doc right now. Try again or contact support.

Written for

Institution
ARE Project Management - PJM - NCARB
Course
ARE Project Management - PJM - NCARB

Document information

Uploaded on
October 13, 2024
Number of pages
8
Written in
2024/2025
Type
Exam (elaborations)
Contains
Questions & answers

Subjects

Content preview

ARE Project Management - PJM - NCARB Practice Exam
Questions And 100% Correct Answers


An architect working on a design-build delivered project visits the site. The architect
perceives unsafe working conditions due to the fact that many of the construction
workers are not wearing hard hats.



How does the architect respond?

A. The architect must directly address the safety measures that should be implemented
immediately by the construction workers. B. Document unsafe conditions in a memo to
the contractor, copied to the owner. C. Document the unsafe working conditions in a
memo to the owner that is also copied to the contractor. D. Request the contractor to
review the safety precautions that need to be taken with the construction workers. -
ANSWER C. Document the unsafe working conditions in a memo to the owner that is
also copied to the contractor.



An architect has a large project with a construction manager (CM) as-contractor. All
designers and engineers have been retained and design is approximately 50 percent
complete. Because of the size of the project, the CM cannot obtain a bond for the entire
contracted project. Multiple smaller construction contracts will be required. The owner
and architect prefer to have all current design and construction team members
continue in their respective roles.



Which of the following delivery methods should the architect recommend to the owner?

A. Design-buildB. CM as-advisor C. Multiple prime D. Design-bid-build - ANSWER B. CM
as-advisor



An owner is proposing to construct a warehouse and has retained the architect to
prepare a building program and to document the owner's requirements. The
programming documents have just been completed.



Which of the following delivery method options should the architect recommend, that
will least require the owner's involvement in completing the project?

, A. Design-bid-build B. Design-build C. CM at-risk D. Integrated project delivery -
ANSWER B. Design-build



A university hires an architect to design a renovation and addition to a performing arts
center. The university would like to utilize an integrated project delivery method and
contract with a series of consultants that each would coordinate their scope of work
with the architect. The work is to be performed in multiple phases and includes the
following:

Restore the original façade of the existing facility built in 1905.

Convert the existing sloping concrete floor performance hall into a new flat floor
performance space.

Renovate existing classrooms to provide new state-of-the-art audio and video
laboratories.

Design a performance hall addition connected to the existing facility via an elevated
walkway.

Identify and address any AHJ or accessibility issues in the existing facility.

Which of the following should the architect recommend the university retain prior to the
schematic design phase? Select the four that apply. - ANSWER A. General contractor

C. Geotechnical engineer

E. Historical preservationist

F. Construction manager



At which of the following is the development of the structural, mechanical, and electrical
designs and the preparation of outline specifications completed? - ANSWER Design
development



Working under an AIA B101, an owner hires an architect to renovate an existing
performing arts center. Delivery via design-bid-build is to be used. The owner has
contracts with an advising construction manager and a series of consultants, each of
whom coordinates his scope of work with the architect.

Rather than the agreed upon 21 days, the owner's theatrical lighting consultant sends
updated drawings to the architect for final coordination 14 days prior to completing the
construction documents. The consultant's updated drawings show a substantial amount
more lighting equipment and materials than previous coordination drawings. The start

Get to know the seller

Seller avatar
Reputation scores are based on the amount of documents a seller has sold for a fee and the reviews they have received for those documents. There are three levels: Bronze, Silver and Gold. The better the reputation, the more your can rely on the quality of the sellers work.
Easton West Virgina University
View profile
Follow You need to be logged in order to follow users or courses
Sold
501
Member since
2 year
Number of followers
221
Documents
21802
Last sold
3 days ago

3.9

111 reviews

5
53
4
21
3
21
2
7
1
9

Recently viewed by you

Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their tests and reviewed by others who've used these notes.

Didn't get what you expected? Choose another document

No worries! You can instantly pick a different document that better fits what you're looking for.

Pay as you like, start learning right away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and aced it. It really can be that simple.”

Alisha Student

Frequently asked questions