This document consists of x20 multiple-choice questions and answers. I got total (A+).

Institution
Course









Whoops! We can’t load your doc right now. Try again or contact support.

Written for

Institution
Course

Document information

Uploaded on
October 11, 2024
Number of pages
5
Written in
2024/2025
Type
Exam (elaborations)
Contains
Questions & answers

Subjects

Content preview

PROJECT MANAGEMENT ASSESSMENT (PRM3701) 07




Question 3
Question text
SWOT Analysis is used to aid in strategic planning
True
False
Question 4
Question text
Jim has been tasked to set up a kiosk for a professional accounting meeting. Which of these
choices below enables him to decide if this is a project or day to day work?
a. An established objective
b. A clear beginning and end
c. Specific time, cost and performance requirements

, d. For internal use
e. Option 1,2 and 3 are correct
Question 5
Question text
One who endorses and lends political support for the completion of a specific project is known as
the
a. Project manager
b. CEO
c. Project sponsor
d. Project lead
e. Sacred cow
Question 6
Question text
A project can have a negative schedule variance and still be ahead of schedule when
a. all budget targets have been achieved.
b. earned value exceeds planned value.
c. progress on the critical path is faster than non- critical path tasks.
d. actual cost exceeds earned value.
e. None of these alternatives is correct.
Question 7
Question text
Which part of the audit report examines in detail the underlying causes of problems, issues, and
successes relative to the project and includes concise, factual review statements of the project?
a. Classification
b. Analysis
c. Recommendations
d. Lessons learned
e. Appendix
Question 8
Question text
This type of closure occurs when the project may never seem to end. At some point the review
group should recommend methods for bringing final closure to this type of project. This is con-
sidered ___________ closure.
a. normal
b. premature
c. perpetual
d. changed priority
e. failed project
Question 9
Question text
Once you have established who the key players are that will determine success, then you initiate
contact and begin to build a relationship with those players. Less effective managers
a. spend the majority of their time outside their office.
b. are able to stay in touch with what is really going on through face-to-face interactions.

Get to know the seller

Seller avatar
Reputation scores are based on the amount of documents a seller has sold for a fee and the reviews they have received for those documents. There are three levels: Bronze, Silver and Gold. The better the reputation, the more your can rely on the quality of the sellers work.
abhengu9 University of South Africa (Unisa)
Follow You need to be logged in order to follow users or courses
Sold
65
Member since
2 year
Number of followers
53
Documents
28
Last sold
10 months ago

3.2

6 reviews

5
2
4
1
3
1
2
0
1
2

Recently viewed by you

Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their tests and reviewed by others who've used these notes.

Didn't get what you expected? Choose another document

No worries! You can instantly pick a different document that better fits what you're looking for.

Pay as you like, start learning right away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and aced it. It really can be that simple.”

Alisha Student

Frequently asked questions