ANSWERS(RATED A)
The schedule activity list:
A. Serves as an extension of the work breakdown structure
B. Is synonymous with the work breakdown structure
C. Is used to create the project scope statement
D. Includes the activity attributes - ANSWER A
Linda is preparing for her upcoming meeting with the board and reviewing the latest reports from her
team. She notes that the schedule variance for the last period was reported as $25,000. Assuming that
number is accurate, which of the following statements must be true?
A. The project must be ahead of budget - Linda should have good news to report to the board
B. The earned value for the project must exceed the planned value by $25,000
C. The schedule performance index must be less than 1
D. The working efficiency index must be 1.25 for this reporting period - ANSWER B
Leads and lags are evaluated, applied, or adjusted in which processes?
A. Report Performance and Control Schedule
B. Develop Schedule and Control Schedule
C. Control Schedule and Control Scope
D. Estimate Activity Durations and Develop Schedule - ANSWER B
What describes the duration a schedule activity or task may be delayed before affecting the early start of
any subsequent or downstream task?
A. Distributed float
B. Negative slack
C. Free float