Verification of performance of inspection and testing programs shall do which of the following to -
Answer✔✔-Verify that the installed system meets the operation requirements of the version of code
when the system was installed, verify the correct operation of the system.
Which of the following shall be done when conducting tests in lead-acid type batteries - Answer✔✔-
Annually conduct a discharge test with the charger disconnected while conducting a load test with full
alarm load or an artificial load,
Area of refuge two-way communication systems are required to be tested in which of the following three
ways - Answer✔✔-Verify Receipt of visual and audible signal at the transmitting and receiving unit,
respectively
How often shall secondary power supply be tested? - Answer✔✔-Annually
How often are video image smoke and fire detectors required to be inspected? - Answer✔✔-Annually
Which two of the following are true regarding acceptable test plans? - Answer✔✔-Shall be documented
with the testing records, shall be written to clearly establish the scope of the testing for the fire alarm or
signaling system.
How often shall fire optic cable connections be inspected? - Answer✔✔-Annually