Lean Bronze Certification Exam Questions with 100% Verified Correct Answers 2024/2025 The concept of the downstream process going to the upstream process to pick up product is called: a. Just in time b. Push system c. Pull system d. visual factory - Correct Answer C. Pull System A multi-step manufacturing process' capacity is limited by one if its workstations. To increase the process' capacity, the factory must: a. Increase the capacity of the constraining workstation b. Increase production starts (work put into the first operation) c. Decrease the utilization of all workstations in the process d. Decrease the utilization of the constraining workstation - Correct Answer a. Increase the capacity of the constraining workstation The optimal number of workers may be determined by: a. Standard cost data b. Line balancing c. Labor and Overhead d. Industry standard - Correct Answer b. Line Balancing Production standards in a lean system should be established by: a. Scheduling managers b. process engineers c. efficiency experts d. Production workers - Correct Answer d. Production workers The greatest contribution of the 5- why analytical tool is that it helps the lean practitioner to identify

Show more Read less
Institution
Lean Bronze Certification
Course
Lean Bronze Certification










Whoops! We can’t load your doc right now. Try again or contact support.

Written for

Institution
Lean Bronze Certification
Course
Lean Bronze Certification

Document information

Uploaded on
October 5, 2024
Number of pages
26
Written in
2024/2025
Type
Exam (elaborations)
Contains
Questions & answers

Subjects

Content preview

Lean Bronze Certification Exam Questions
with 100% Verified Correct Answers
2024/2025
The concept of the downstream process going to the upstream process to pick up product is called:

a. Just in time

b. Push system

c. Pull system

d. visual factory - Correct Answer C. Pull System



A multi-step manufacturing process' capacity is limited by one if its workstations. To increase the
process' capacity, the factory must:

a. Increase the capacity of the constraining workstation

b. Increase production starts (work put into the first operation)

c. Decrease the utilization of all workstations in the process

d. Decrease the utilization of the constraining workstation - Correct Answer a. Increase the capacity
of the constraining workstation



The optimal number of workers may be determined by:

a. Standard cost data

b. Line balancing

c. Labor and Overhead

d. Industry standard - Correct Answer b. Line Balancing



Production standards in a lean system should be established by:

a. Scheduling managers

b. process engineers

c. efficiency experts

d. Production workers - Correct Answer d. Production workers



The greatest contribution of the 5- why analytical tool is that it helps the lean practitioner to identify
the:

,a. solution to the problem

b. root cause of the problem

c. number of occurrences of the problem

d. person who caused the problem - Correct Answer b. root cause of the problem



To identify waste in a selected production line, the first step is to:

a. Perform 5-S activities to organize the line

b. create a current state value stream map

c. determines the specific material that runs in the line

d. perform a time and motion study - Correct Answer b. create a current state value stream map



Which of the following is considered value-added work?

a. Eliminating all defects and the need for rework

b. Empowering employees to establish their own work standards

c. Changing the shape or character of a product or assembly

d. activities that must be performed under present work conditions - Correct Answer c. Changing the
shape or character of a product or assembly



The basis of the Toyota Production System is:

a. the monitoring of time vs. order and delivery

b. Five S, 5 Why's and the 7 wastes

c. the complete elimination of waste

d. standardized work and visual factory - Correct Answer c. the complete elimination of waste



The ultimate goal of lean is the total elimination of:

a. downtime

b. overtime

c. Waste

d. Errors - Correct Answer c. Waste



The worst waste of all, because it opens the door for other kinds of waste is:

, a. Transport

b. Overprocessing

c. Overproduction

d. motion - Correct Answer c. Overproduction (Mother of all wastes)



A Value Stream Map is a tool to:

a. Help you identify which workers are poor performers

b. Enable managers to better understand their backlog

c. Assist you in identifying and eliminating all forms of waste

d. Assist managers to better understand their on-time delivery - Correct Answer c. Assist you in
identifying and eliminating all forms of waste



In a 5S program, the purpose of red tagging is to:

a. provide visual management of WIP

b. Identify broken equipment for repair

c. Highlight processes for continuous improvement

d. Identify material for potential removal - Correct Answer d. Identify material for potential removal



In a process with a Takt time of 3 minutes and a pack out qty of 35 parts, the Pitch is:

a. 35 minutes

b. 90 minutes

c. 105 minutes

d. 11.66 minutes - Correct Answer c. 105 minutes (Pitch formula; Pitch = takt time x pack out qty) (3x
35= 105)



For a production facility working five days per week (one 8-hour shift with 3 Ten-minute breaks), the
customer demand is 2700 units per week. What is the Takt time this facility should produce to?

a. one unit every 54 seconds

b. one unit every 10 seconds

c. one unit every 50 seconds

d. one unit every 57 seconds - Correct Answer c. one unit every 50 seconds

Takt time = available working time (AWT) / customer demand (CD)

Get to know the seller

Seller avatar
Reputation scores are based on the amount of documents a seller has sold for a fee and the reviews they have received for those documents. There are three levels: Bronze, Silver and Gold. The better the reputation, the more your can rely on the quality of the sellers work.
Winfred West Virgina University
View profile
Follow You need to be logged in order to follow users or courses
Sold
756
Member since
3 year
Number of followers
473
Documents
7353
Last sold
4 days ago
StudySmart

Revising without a good structure can be so frustrating but with StudySmart you are able to get revision questions, summary notes and exams to help you pass with flying colors

3.9

158 reviews

5
78
4
28
3
27
2
8
1
17

Recently viewed by you

Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their tests and reviewed by others who've used these notes.

Didn't get what you expected? Choose another document

No worries! You can instantly pick a different document that better fits what you're looking for.

Pay as you like, start learning right away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and aced it. It really can be that simple.”

Alisha Student

Frequently asked questions