The project duration in a network can be determined by the largest
value of which variable associated with the critical path?
A. Slack time
B. Earliest finish time
C. Activity time
D. Earliest start time - answer B. Earliest finish time
A functional organizational structure requires that the project be
A. housed in either the accounting or finance department.
B. managed by a company executive.
C. led by a project manager who can negotiate assistance from
personnel in other functional areas.
D. housed in several departments or functional areas. - answer C.
led by a project manager who can negotiate assistance from
personnel in other functional areas.
Crash time is defined as
A. the shortest possible time to complete an activity.
B. the time necessary to complete an activity under abnormal
conditions.
C. the activity time associated with any management intervention.
D. the difference between earliest start time and earliest finish
time. - answer A. the shortest possible time to complete an
activity.
complete verified solutions
2024
The project duration in a network can be determined by the largest
value of which variable associated with the critical path?
A. Slack time
B. Earliest finish time
C. Activity time
D. Earliest start time - answer B. Earliest finish time
A functional organizational structure requires that the project be
A. housed in either the accounting or finance department.
B. managed by a company executive.
C. led by a project manager who can negotiate assistance from
personnel in other functional areas.
D. housed in several departments or functional areas. - answer C.
led by a project manager who can negotiate assistance from
personnel in other functional areas.
Crash time is defined as
A. the shortest possible time to complete an activity.
B. the time necessary to complete an activity under abnormal
conditions.
C. the activity time associated with any management intervention.
D. the difference between earliest start time and earliest finish
time. - answer A. the shortest possible time to complete an
activity.