GFEBS Master Data Plant Maintenance
Process Overview Post Test Study Guide
Maintenance Plan Costing is based on all aspects required to perform the preventive
maintenance task as outline in the PM plan. - Correct Answer✔️✔️-TRUE
The Project Structure Controller and Project Planned WBS Cost Controller are involved
in the Re-Prioritize IJO Project List step of the Annual Work Plan. - Correct Answer✔️✔️-
TRUE
Operations Work Orders are used to execute Preventive maintenance plans. - Correct
Answer✔️✔️-FALSE
After the demand maintenance work is completed, the Order Maintainer sets the work
order to technically complete (TECO), automatically settling any cost posted to the
order, and finally sets the order to “Business closed.” - Correct
Answer✔️✔️-TRUE
Methods of Physical Inventory count include: continuous inventory, cycle counting, and
random checking. - Correct Answer✔️✔️-FALSE
Preventive and Demand Work Orders rely on correct WBS numbers in order to get
funding so that work can be accomplished. - Correct Answer✔️✔️-TRUE