UPDATED Exam Questions and
CORRECT Answers
Most installation procedures start at the machine foundation substructure because?
a. the manual says so
b. the foundation introduces misalignments in the equipment
c. the foundation moves
d. the foundation is inconsistant - Correct Answer- b. the foundation introduces
misalignments in the equipment
When installing on concrete, millwrights usally start their installation on?
a. level ground
b. tempered ground
c. the assumption that they will have to install anchor bolts
d. exsiting anchor bolts - Correct Answer- d. exsiting anchor bolts
Foundations are usually constructed with
a. minus elevation
b. positive elevation
c. plane elevation
d. on set elevation - Correct Answer- a. minus elevation
This eliminates foundation shrinkage, 38mm is left for shims and grouting
What is used to firmly secure the machine baseplate or soleplates to a concrete foundation? -
Correct Answer- Anchor Bolts
How far should straight anchor bolts without deformed ends be set into the foundation?
a. 45mm