Which activities fall under the category of quality assurance?
- Performing a sample test of 10% of the alarm devices
- Checking every concrete delivery ticket to ensure the mix matches specifications
- Spot checking a subcontractor's inspection checklist
- Flooding a roof with water to see if it leaks. - Answer-Performing a sample test of 10%
of the alarm devices.
Checking every concrete delivery ticket to ensure the mix matches specifications.
Flooding a roof with water to see if it leaks.
A Quality Plan should include which of the following procedures? Choose all that apply.
- Steps to submit a high-quality pay application
- Submittal review and distribution
- RFI templates and distribution
- How to get a security badge (if a secure site) - Answer-Submittal review and
distribution
RFI templates and distribution
True or False? The owner often hires a 3rd party to inspect scopes such as concrete,
earthwork, and paving. - Answer-True
True or False? Addressing the topic of "deficiencies" does not belong in a quality plan
because that represents poor quality. - Answer-False
What are typical items addressed in a Stormwater Management Plan? Choose all that
apply.
- Stormwater Reduction Devices (SRDs)
- Procedures for inspection, maintenance, and reporting
- A plan for final stabilization at the end of the project
- Best Management Practices (BMPs) - Answer-Procedures for inspection,
maintenance, and reporting
A plan for final stabilization at the end of the project
Best Management Practices (BMPs)
True or False? Stormwater violations can include a fine AND imprisonment. - Answer-
True
What are examples of Vehicle Tracking Control (VTCs)? Choose ALL answers that
apply.
, - Large steel grates (like a cattle grate)
- Beacons used to track vehicles off-site (to see if they are tracking soil on the streets
- Spill kits (which must be on every job site)
- Large rocks - Answer-Large steel grates (like a cattle grate)
Large rocks
What are common types of submittals? Choose all that apply
- Physical Samples
- Shop Drawings
- Payment Applications
- Product Data - Answer-Physical Samples
Shop Drawings
Product Data
What are the common status options for a submittal reviewed by the Design Team?
- Approved
- No Exceptions Taken
- Revise and Resubmit
- Exceptions as Noted - Answer-No Exceptions Taken
Revise and Resubmit
Exceptions as Noted
What are the main objectives of a Request for Information? Choose all that apply.
- To incorporate change that has a cost impact
- To document changes that have a schedule impact
- To clarify conflicting or missing information
- To propose a new solution - Answer-To clarify conflicting or missing information
To propose a new solution
What is the phrase used in this lesson that summarizes the importance of accurate
Jobsite records?
- Whoever is careless with the truth in small matters cannot be trusted with important
matters
- Writing is easy. All you have to do is cross out the wrong words.
- If it wasn't in writing, It didn't happen
- Well done is better than well said - Answer-If it wasn't in writing, It didn't happen
What are typical items included in Jobsite Records? Choose all that apply.
- Field observations
- Inspection documentation
- Record of behavior
- Safety incidents - Answer-all of the above
What are items typically noted on a Daily Report? Choose all that apply.
- The weather
- Questions to the Design Team