Overhead cranes with more than one hoisting unit shall have what? - CORRECT
ANSWER its rated load marked on it
What is the purpose of the "E" (Emergency) stop on an overhead crane? - CORRECT
ANSWER removes power to entire crane
How often does O.S.H.A. require a written wire rope inspection? - CORRECT ANSWER
once a month
Most loads should be rigged to within how many degrees of level? - CORRECT
ANSWER five
According to ASME B30.2, what is the safety factor for rigging? - CORRECT ANSWER
5 to 1
According to O.S.H.A. frequent Inspections shall be performed when? - CORRECT
ANSWER daily to monthly
According to ASME B30.2 a frequent inspection must be performed by a? - CORRECT
ANSWER designated person
According to ASME B30.2, the maximum twist of the hook can't exceed? - CORRECT
ANSWER 10 degrees
When inspecting electrical contacts, what are the signs they are bad? - CORRECT
ANSWER pitted or burned
According to ASME B30.2, what type of fire extinguisher is required for overhead cranes?
- CORRECT ANSWER 10BC
, LATEST OVERHEAD CRANE TEST 2024-2025
QUESTIONS WITH 100% CORRECT ANSWERS
Before leaving an overhead crane unattended, attached loads should be? - CORRECT
ANSWER lowered to the floor
Before using your hand to steady any load, you should? - CORRECT ANSWER follow
company policy
According to OSHA, the rated capacity of all overhead cranes shall be? - CORRECT
ANSWER clearly marked on the side of the crane
When attaching spreaders to any load, you must keep in mind of what? - CORRECT
ANSWER the lower the spreader angle the greater the tension
What is the order of hitch strength? - CORRECT ANSWER basket, vertical, choker
According to OSHA, the maximum hook throat opening must not exceed what? -
CORRECT ANSWER 15% of its original size
How many cubic feet is in a rectangular object that measures 5 ft. X 3 ft. X 2 ft.? -
CORRECT ANSWER 30 cubic feet
An object weighs 150 lbs per cubic foot and measures 4 ft. X 3 ft. X3 ft., what is its
weight? - CORRECT ANSWER 5,400 lbs
According to OSHA, how many wraps must be left on the hoist drum of an overhead
crane with the hook at its lowest position? - CORRECT ANSWER 3 wraps
The upper limit switch of all overhead cranes shall be tested every? - CORRECT
ANSWER shift