In MS Project, which button do you click for subordination?
a. Link
b. Indent
c. Resource Assign
d. Resource Sheet Correct answer-b. Indent
In MS Project, which button do you clink on to indicate precedence?
a. Link
b. Indent
c. Resource Assign
d. Resource Sheet Correct answer-a. Link
In MS Project to view project cost and duration, you must click on
a. Project on the menu bar, then project information and then statistics
b. Tools on the menu bar and then Project information underneath
c. Functions on the menu bar and then project statistics underneath Correct answer-a.
Project on the menu bar, then project information and then statistics
,Jim Burns, ISQS 4350, Final Exam; Questions &
Answers 100% Solved
In MS Project, to see the activity and phase costs you must
a. Change the table in the Gantt view to "cost"
b. Insert a cost column in the entry table next to the duration column
c. Print a cost report
d. Any of the above Correct answer-d. Any of the above
For MS Project to cost your project, it needs to know
a. resource hourly costs
b. activity fixed costs
c. stakeholder charges
d. all of the above
e. a and b only Correct answer-e. a and b only
In MS Project, durations of phases containing one or more subordinate tasks, can be
a. changed manually by the user
b. specified only by MS Project
c. none of the above
d. a or b only Correct answer-b. specified only by MS Project
, Jim Burns, ISQS 4350, Final Exam; Questions &
Answers 100% Solved
In MS Project, task information is entered in which view?
a. Resource sheet
b. PERT chart
c. Gantt chart
d. task sheet Correct answer-c. Gantt chart
In MS Project, the view that exhibits the network diagram is the
a. Resource sheet
b. PERT chart
c. Gantt chart
d. task sheet Correct answer-b. PERT chart
In MS Project, the critical path is
a. exhibited in red
b. not calculated or found
c. exhibited on the PERT chart only
d. replaced with the critical chain Correct answer-a. exhibited in red