Answers % Correct
Hard bid low price Correct answer-Owner hires architect
Architect designs
Contractors bid
Awarded to low bidder
Competitive sealed proposals Correct answer-Involves criteria other than price when
awarding contract
Weight given to each criteria that will be considered
Criteria: (changes)
- Cost
- Previous experience
- Qualification of staff
- Financial stability
- Project schedule
Construction Manager at Risk CMAR Correct answer-Construction manager hired in
design phase to assist designer in constructability.
CM agrees to Guaranteed max price
CM works w owner and architect
, COSC 275 Exam 2 Palmer; Questions and
Answers % Correct
Design Build Correct answer-Only one contract - between owner and design-build
contractor
May be one entity or contractor and architect in a contract.
Wasn't allowed for a while
most common steel type?
a) A529 - 50 KSI
b) A36 - 36 KSI Correct answer-a) A529 - 50 KSI
Weathering steel
a)A242
b)A585
c) both Correct answer-c) Both
Flag weld symbol meaning Correct answer-Field weld (on site)
4 types of envelope construction Correct answer-Tilt Wall
Stud with veneer
Masonry
Glass