FINAL ESTIMATES LEVEL 2 Questions & answers

Institution
Course









Whoops! We can’t load your doc right now. Try again or contact support.

Written for

Course

Document information

Uploaded on
July 4, 2024
Number of pages
7
Written in
2023/2024
Type
Exam (elaborations)
Contains
Questions & answers

Subjects

Content preview

FINAL ESTIMATES LEVEL 2

On multi FIN project numbers under one contract, the Asphalt is reported on the
certification, by the CONTRACTOR, under what Project FIN Number? - ANS-The
Contractor shows the Asphalt on the lead FIN project number

A roadway is being constructed and has a Subsoil Excavation Quantity of 835 CY, a
Regular Excavation Quantity of 250 CY and an embankment Quantity of 1040 CY.
Based upon this information, the Final Quantity to be paid for embankment will be? -
ANS-1875 CY

Which Document is used to authorize payment from original contingency Amount? -
ANS-Work Order

Friction Course (FC-12.5) Straight edge Deficiency: A straightedge deficiency was left in
place at no pay. Calculate the equivalent tonnage at no pay. ( pay to appropriate
accuracy) Gmm= 2.417, thickness =1.5 inches, road width =12 feet, length of deficiency
= 5 ft. (this occurred 25 feet from the bridge deck) - ANS-8.4 Tons

Overruns or Underruns must be explained when? - ANS-A pay item overruns or
underruns $10,000 or more.

Prices are adjusted on each progress estimate to reflect increases or decreases in the
price of fuel for contracts with original Contract Time: - ANS-In excess of 120 calendar
days.

Which of the following is an authorized way to modify the contract, once it has been
executed? - ANS-Work Orders and Supplimental Agreements

Of the Contract Documents listed below which one would govern? - ANS-Special
Provisions

Why is it important to run a progress estimate soon after Final Acceptance? - ANS-So
the estimate can be paid through EED quickly to prevent interest.

On Financial Project No.000101-1-52-01, which is a conventional project, the notice to
proceed is dated December 1, 2015 and the contract time is to start 16 days after the
Notice to Proceed per the contract. The Contractor begins work on December 18, 2015

, and the project is Final Accepted on December 31, 2015. There are no added weather
or other reasons. What is the 1st chargeable day and how many total days should be
recorded in the Contract Time File? - ANS-12/17/2015 with 15 chargeable days.

On Lump Sum Contracts, upon Final Acceptance, the Project Administrator will send? -
ANS-The Offer of Final Payment

Field Records for multiple jobs, same contract, should be kept? - ANS-In seperate Field
Books & In seperate files within Project Solve and EDMS

On Lump Sum Project, A Superpave Asphalt Course item requires a Composite Pay
Factor (CPF) adjustment. What is the total dollar adjustment amount?
Lot 1 with 2000 Tons and a CPF of 0.99
Lot 2 with 4000 Tons and CPF of 0.99
Lot 3 with 4000 Tons and CPF of 1.00
Lot 4 with 4000 Tons and a CPF of 1.00 - ANS-$5425.20

Under the current Specifications for Lump Sum Projects, the Project Administrator will
approve and pay the Final Estimate? - ANS-False

Original Terrain line sections: - ANS-A)Represent the terrain prior to Contruction
B) Are necessary to establish earthwork quantities
C) Must be shown on cross sections.
ALL OF THE ABOVE

The plans show the designer calculations for Clearing & Grubbing with a total of 3.2
Acres to be cleared and grubbed. During the Construction, a plan error was
encountered which required the clearing and grubbing of an additional 800 SY. This
required an adjustment to the original Lump Sum Pay Item. Calculate the adjusted Final
Pay Quantity. The secondary unit is in Acres not SY. Note 1 Acre= 4840 SY:
Pay Item= Clearing and grubbing
Original Quantity = 1.0 Lump Sum - ANS-3.2 Ac x 4840 SY= 15488 SY
15488 + 800 SY = 16288 SY
16288 SY/15488 SY = 1.052 Lump Sum

The Prime Contractor is required to certify previous payments for? - ANS-1st tier
Subcontractors and Suppliers

Borrow Excavation is paid for as a? - ANS-Final Measurement

Reviews from verified buyers

Showing all reviews
5 months ago

5.0

1 reviews

5
1
4
0
3
0
2
0
1
0
Trustworthy reviews on Stuvia

All reviews are made by real Stuvia users after verified purchases.

Get to know the seller

Seller avatar
Reputation scores are based on the amount of documents a seller has sold for a fee and the reviews they have received for those documents. There are three levels: Bronze, Silver and Gold. The better the reputation, the more your can rely on the quality of the sellers work.
GOLDSOLUTIONS Chamberlain College Of Nursing
Follow You need to be logged in order to follow users or courses
Sold
4993
Member since
2 year
Number of followers
60
Documents
17179
Last sold
16 hours ago

4.2

70 reviews

5
45
4
8
3
9
2
3
1
5

Recently viewed by you

Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their tests and reviewed by others who've used these notes.

Didn't get what you expected? Choose another document

No worries! You can instantly pick a different document that better fits what you're looking for.

Pay as you like, start learning right away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and aced it. It really can be that simple.”

Alisha Student

Frequently asked questions