CM 1011 - Chapter 6 & 9 Questions with 100% Actual correct answers | verified | latest update | Graded A+ | Already Passed | Complete Solution

Rating
-
Sold
-
Pages
10
Grade
A+
Uploaded on
26-06-2024
Written in
2023/2024

CM 1011 - Chapter 6 & 9 Questions with 100% Actual correct answers | verified | latest update | Graded A+ | Already Passed | Complete Solution

Institution
Course









Whoops! We can’t load your doc right now. Try again or contact support.

Written for

Institution
Study
Course

Document information

Uploaded on
June 26, 2024
Number of pages
10
Written in
2023/2024
Type
Exam (elaborations)
Contains
Questions & answers

Subjects

Content preview

CM 1011 - Chapter 6 & 9
What is an estimate? - ANS-An estimates is an educated guess and is formed of the cost to the
contractor.

It forms the basis of a contractor's budget.

includes:
-costs of labor and labor burdens
- materials and taxes on materials
- equipment
- subcontracts
- direct project overhead costs

Should NOT include:
-general overhead or profit

A bid.... - ANS--amount for which a contractor is willing to do the project.

-forms the basis of the Owner's budget

-estimate amount PLUS general overhead/ profit

Direct project overhead costs - ANS-costs that are not identified with any one work item, but are
needed for the project.

no project = no direct project overhead costs

Office overhead/ general overhead, - ANS-Cost of operating the home office

Office overhead/ general overhead = exists whether there is a project or not.

The estimate must be low enough to get the bid, but - ANS-high enough to make a profit off of.

Characteristics of a good estimator - ANS-1. knowledgeable in construction techniques & good
visualization skills
2. detailed oriented and thorough
3. Good with numbers and statistics
4. familiar with material costs and computer applications
5. Work well under deadline pressures
6. Be practical but creative

, Two main factors of a project? - ANS-1. Project Size
2. Project complexity

The larger the project is the more opportunity there is to - ANS-increase efficiencies around any
particular activity.

Economy of Scale - ANS-is a proportionate saving in costs gained by an increased level of
production.

As complexity increases, - ANS-so does cost!

What could cause a delay in the project? - ANS-Fabricated materials with long lead times

What impacts productivity of a project? - ANS-- complexity
- project details

Name some factors that increase the cost of a project? - ANS-1. Shape of facility
2. Height of the facility
3. Unique materials or applications

Liquidated damages - ANS-A daily amount of money paid by the contractor to the owner for
each day that the project fails to meet the completion date specified in the contract.

Not all contracts contain a liquidated damages clause.

Lead Time - ANS-The amount of time it takes for a product or equipment to be delivered to the
job site. Products that have a long delivery time are called long lead-time items and require
special planning considerations.

What impacts has the location of the project? - ANS--ease procurement and delivery of
materials, labor, equipment
-availability and cost of labor

Time of construction - ANS--Estimator must anticipate fluctuations of costs during various
stretches of time e.g. notice to proceed not received for 2 years, not to have enough funds to
sustain this

How do the seasons impact projects? - ANS-Seasonal weather changes impact estimate and
eventual cost

Quality of Work - ANS-Quality of a project is defined by the standards et forth in the
specifications.

Quality clearly impacts project cost.
$7.99
Get access to the full document:

100% satisfaction guarantee
Immediately available after payment
Both online and in PDF
No strings attached


Also available in package deal

Get to know the seller

Seller avatar
Reputation scores are based on the amount of documents a seller has sold for a fee and the reviews they have received for those documents. There are three levels: Bronze, Silver and Gold. The better the reputation, the more your can rely on the quality of the sellers work.
DoctorHkane Havard School
Follow You need to be logged in order to follow users or courses
Sold
732
Member since
4 year
Number of followers
168
Documents
22458
Last sold
1 day ago

Explore my Stuvia collection for essential study aids: test banks, exams, summaries, and cases. With five years of expertise as an academic writer, I have honed my skills in crafting top-notch essays, exams, and research dissertations. My proficiency lies in producing well-structured and thoroughly researched content that meets academic standards. I am adept at handling various subjects and ensuring a seamless flow of ideas. Whether it's delivering compelling arguments in essays, creating challenging yet fair exam questions, or delving into in-depth research for dissertations, my experience equips me to excel in diverse academic writing tasks. I pride myself on meeting deadlines and maintaining the highest quality in every piece I produce. REACH ON iamnjokikelvin1@gmail

Read more Read less
4.6

386 reviews

5
308
4
29
3
21
2
10
1
18

Recently viewed by you

Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their tests and reviewed by others who've used these notes.

Didn't get what you expected? Choose another document

No worries! You can instantly pick a different document that better fits what you're looking for.

Pay as you like, start learning right away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and aced it. It really can be that simple.”

Alisha Student

Frequently asked questions