Questions & Correct Answers 2024/2025
1. A configuration management program should focus on ensuring designs
are traceable to capability needs, developmental changes are controlled
and documented, interfaces are well-defined and understood, and
_______________________________. - ANS -All product documentation is
consistent with its supporting information.
2. Which technical review is held during the Technology Maturation and Risk
Reduction phase to ascertain progress in defining system technical
requirements? - ANS -System Requirements Review (SRR)
3. Program cost increases and schedules slips are most likely caused by
__________________, changes to the design, and changes to the
production processes. - ANS -Changes to user capability needs.
,4. What group is used to help control the configuration of external
interfaces for a system? - ANS -Interface Control Working Group
5. Your new-start program was approved this year's Authorization Bill and
you are currently operating under Continuing Resolution Authority. To
avoid losing a top engineering from your program, you authorial the
Contractor to begin work since you expect the Appointment Bill to be
signed next week. You are now in conflict with the _____. - ANS -Anti-
Deficiency Act
6. Cost, schedule, and performance parameters are interrelated and a
change in one parameters can affect the others. Therefore it is important
to involve all the key stakeholders when considering changes to
Acquisition Program Baseline (APB). - ANS -True
7. The Joint Interoperability Test Command (JITC) verifies
________________ through the field assessment of systems during
, exercises and contingencies, and provides certificates of _____________
upon validation. - ANS -Interoperability performance/ interoperability.
8. Which of the following configuration baselines provides the details from
which a contractor can transition from design to production of a system? -
ANS -Product Baseline
9. In the interest of independent reporting, Developmental Test and
Evaluation (DT&E) and Operational Test and Evaluation (OT&E) activities
may NOT be integrated. - ANS -False
10.Changes are typical in acquisition programs; therefore, it is important to
develop a sound configuration management strategy, place the
Government in control of each element of the baselines, and design
enough flexibility into the system to handle enhancements. - ANS -False.