Use the information below to construct a project network using the activity-on-
node (AON) method in order to answer questions that follow.
Activity ID Predecessor Duration (in days)
A None 3
B A 1
C A 4
D B 1
E B, C 2
F E 8
G D 2
H E 3
I F, G, H 1
J I 1
Question 1
What is the earliest start (ES) time for activity I?
a.
7
1
, 2024 – S1 – PRM3701 – ASSESSMENT 3 – Q&A
b.
17
c.
12
d.
15
e.
9
Feedback
AON network will be provided after the assessment closes
The correct answer is:
17
Question 2
If Activity F is delayed by 2 days. What will happen to the rest of the project?
a.
The whole project will be delayed by 2 days
b.
There will be no impact on the project
Feedback
AON network diagram will be provided once the assessment closes
The correct answer is:
The whole project will be delayed by 2 days
Question 3
What is the late finish (LF) time for activity E?
a.
9
2
Assessment 3
Started on Thursday, 4 April 2024,
State Finished
Completed on Thursday, 4 April 2024,
Time taken
Marks 10.00/10.00
Grade 100.00 out of 100.00
Use the information below to construct a project network using the activity-on-
node (AON) method in order to answer questions that follow.
Activity ID Predecessor Duration (in days)
A None 3
B A 1
C A 4
D B 1
E B, C 2
F E 8
G D 2
H E 3
I F, G, H 1
J I 1
Question 1
What is the earliest start (ES) time for activity I?
a.
7
1
, 2024 – S1 – PRM3701 – ASSESSMENT 3 – Q&A
b.
17
c.
12
d.
15
e.
9
Feedback
AON network will be provided after the assessment closes
The correct answer is:
17
Question 2
If Activity F is delayed by 2 days. What will happen to the rest of the project?
a.
The whole project will be delayed by 2 days
b.
There will be no impact on the project
Feedback
AON network diagram will be provided once the assessment closes
The correct answer is:
The whole project will be delayed by 2 days
Question 3
What is the late finish (LF) time for activity E?
a.
9
2