CDT Practice Questions and Answers latest Actual Exam
CDT Practice Questions and Answers latest Actual Exam Sheet keynote or reference keynote - CORRECT ANSWER-a notation on a single drawing sheet "A facility's "life cycle" includes all of the following EXCEPT: a. Project conception b. Financing c. Construction d. Facility management" - CORRECT ANSWER-1. b - PRM 1.4 Life cycle Stages: Conceptions, Delivery Method, Design, Psrocurement, Construction, What does CSI's UDS do ? what does it stand for ? - CORRECT ANSWER-UDS uniform drawing system CMa stands for... - CORRECT ANSWER-Construction Manager as Advisor "The objective of the competitive bidding process is: a. To ensure that all qualified bidders may submit bids on public work projects b. To ensure that public works contracts are always awarded to the lowest bidders c. To ensure that the intent of the governing public laws is maintained in the awarding of contracts d. To ensure that the cost of the project is reasonable and consistent with the prevailing conditions in the building industry" - CORRECT ANSWER-2. d - PRM 3.4 What is included in PART 3 of SectionFormat? - CORRECT ANSWER-PART 3- EXECUTION: describes field/site installation or application, including preparatory actions and post-installation cleaning and protection. Field/site-built assemblies and field/site-manufactured products and systems are included. "A unit price contract or contract portion is used when: a. Extent of work cannot be fully determined or where actual quantities cannot be accurately calculated. b. Extent of work is known, but the owner desires a break-out cost for portions of the work. c. It is anticipated that bidders will not examine soil bearing reports prior to submitting bid. d. Bidding quantities of equipment. Review: PDPG 7.1.6.2" - CORRECT ANSWER-"a. Extent of work cannot be fully determined or where actual quantities cannot be accurately calculated. Use of unit prices, allowances and alternates should always be limited to those items required for accurate bidding, in order to keep bidding documents and processes as simple as possible." "The contractual relationship governed by the Conditions of the Contract is between: a. Owner and contractor b. Architect/engineer and contractor c. Owner and Subcontractors d. Owner, contractor, and architect/engineer Review: PDPG 5.5 and 11.3.9" - CORRECT ANSWER-"a. Owner and contractor The owner and the contractor are the parties to the construction contract, hence they are subject to the Conditions of the Contract. Yes, the duties of the architect are described in the Conditions of the Contract, but they are governed by the separate Owner/Architect or Owner/Engineer Agreement." How long does a contractor required to execute corrections in the Work after Substantial Completion? - CORRECT ANSWER-one year "Which of the following would be included in Available Information? a. Bid security requirements b. Environmental Impact Statement c. Time of completion to construct the project d. Description of the Work Review: PDPG 11.4.5" - CORRECT ANSWER-"b. Environmental Impact Statement Available Information is the place to provide reference information such as this that doesn't belong in the contract. Bid security info? In the Instructions for Procurement. Time of Completion? It's contractual - where would you put it? Description of Work? Name the Division 01 section where that belongs." "Instructions for Procurement: a. Are used only on private projects b. Frequently are standard industry forms c. May include the geotechnical report as an attachment d. Are binding upon the Contractor Review: PDPG 11.4.4 " - CORRECT ANSWER-"b. Frequently are standard industry form
Written for
- Institution
- Cdt
- Course
- Cdt
Document information
- Uploaded on
- May 30, 2024
- Number of pages
- 31
- Written in
- 2023/2024
- Type
- Exam (elaborations)
- Contains
- Questions & answers
Subjects
- cma stands for
-
cdt practice questions and answers latest actual e
-
sheet keynote or reference keynote
Also available in package deal