Contractors Questions and answers latest
update
The _________ consists of daily checks of the work to assure continuing compliance with contract
requirements
Follow-up Phase
Design-Build contracts require
The QC Manager to be in place and take an active role in the review and coordination of the design.
Which of the following is included in all three phases of the Three Phases of Control?
Safety
The purpose of Construction Quality Management is to
Achieve the quality established by properly developed requirements through the combined
responsibility, but separate, efforts of contractors and government personnel
Testing is extremely important in construction quality management and is performed by
Both the contractor and the government
The primary purpose of the Three-Phase Control System is to
Require the contractor to plan, schedule, and perform quality management actions to assure work
meets all specified quality standards
Quality Assurance Personnel have the responsibility to
Require the contractor to maintain the quality specified in the plans and specifications
The _________________ is the appropriate time to assure that all materials and/or equipment have
been tested, submitted, and approved
Preparatory Phase
The Preconstruction Conference and Coordination and Mutual Understanding Meeting Are
Conducted prior to the commencement of any physical construction work
Contractor testing procedures:
Are specified in the technical specs, outlined in the QCP, and addressed at Coordination and Mutual
Understanding Meeting
The Quality Control Plan contains
Identification of individual quality quality control personnel, including name, qualifications, assigned
duties, responsibilities and authorities.
Tests that are unannounced, randomly performed, and repeat quality control tests are
Quality assurance tests