Project Assurance Is responsible for monitoring all the aspects of the project's performance, independenProgress theme purpost of the Project Manager. e -Defines the way that the project progress is measured and compared to performance targets -Progress enables a forecast of the continuing project viability 5 Targets of Prince2 Agile - Be on time and hit deadlines, - Protect the level of quality, - Embrace change, - Keep teams stable; do not add people to a team in order to try to go faster - Accept that the customer doesn't need everything Risk theme purpose + tailored to agile The purpose of the risk theme is to identify, assess and control uncertainty and as a result, improve the ability of the project to succeed In prince2/agile, risks are reduced by iterative and incremental delivery and by daily stand-up meetings Change theme purpose + tailored to agile To identify, assess and control any potential and approved changes to the baseline Prince2 Agile: control significant changes, embrace the others Plans theme purpose + tailored to agile Recommends different levels of plan to facilitate communication and control from the differing perspectives of the project organization Plans enable the business case to be realized Prince2 Agile: Empiricism has many advantages, and to use PRINCE2 in an Agile environment this needs to be fully understood and embraced. PRINCE2 plans need an end date to justify and authorize the plans, to have a baseline for progress and to show that the Minimal Viable Product (MVP) is created in time. Organization theme purpose Defines the project organization structure and roles Defines the approach to communicating and engaging with stakeholders Prince2 Agile: enable self-organization by management by exception Scrum Master Coach or facilitator, who serves the product owner, development team, and the organization Project Product Description Describes what the projet has to produce to obtain customer acceptance Issue Report A relevant event that has happened, was not planned and requires management action. It could be a problem, benefit, query, concern, change request or risk that has occurred. 7 Principles Continued Business Justification, Learn from Experience, Define Roles and Responsibilities, Manage by Stages, Manage by Exception, Focus on Products, Taylor to the Environment 7 Processes Starting Up a Project Initiating a Project Directing a Project Controlling a Stage Managing Product Delivery Managing Stage Boundaries Closing a Project 7 Themes Business Case, Organisation, Quality, Plans, Risks, Change, Progress Starting Up a Project - process Ensures that the prerequisites for initiating a project are in place by answering the question: Do we have a viable and worthwhile project? Initiating a Project - process Establishes a solid foundations for the project and to enable the organization to understand the work that needs to be done including a plan Directing a Project - process To enable the project board to be accountable for the project's success by making key decisions and exercising overall control while delegating day-to-day management of the project to the project manager Controlling a Stage - process Helps to assign and monitor work, deal with issues such as change and risk, report progress to the project board, and take actions to ensure that the stage remains within tolerance limits. Managing a Product Delivery - process -To control the link between the project manager and the team manager(s) by agreeing the requirements for acceptance, execution, and delivery -The role of the team manager(s) is to coordinate an area of work that will deliver one or more of the project's products Managing a Stage Boundary - process Provides the project board with sufficient information to review the success of the current stage, approve the next stage, and confirm the continued business justification. Closing a Project - process Provides a fixed point that confirms the acceptance of the project's products and evaluates the project's performance along with possible lessons learned from this project. Management products 26 management products that support the PRINCE2® method such as •Business Case •Checkpoint report •Highlight report •Project brief •Project initiation documentation •Project product description •Work package Project Brief Ensures that the project has agreed upon and well-defined starting point Describes purpose, cost, time and performance requirements, and the constraints for a project. It is created pre-project Business Case Document that provides the justification for starting and continuing the project Continually referenced during the project to ensure continued business justification still exists Work Package CONTINUED......

Show more Read less
Institution
Course









Whoops! We can’t load your doc right now. Try again or contact support.

Written for

Course

Document information

Uploaded on
April 4, 2024
Number of pages
9
Written in
2023/2024
Type
Exam (elaborations)
Contains
Questions & answers

Subjects

Content preview

Prince2 Agile Foundation QUESTIONS
AND ANSWERS GRADE A+ GURANTEED

Project Assurance
Is responsible for monitoring all the aspects of the project's
performance, independent of the Project Manager.
Progress theme purpose
-Defines the way that the project progress is measured and compared
to performance targets
-Progress enables a forecast of the continuing project viability
5 Targets of Prince2 Agile
- Be on time and hit deadlines,
- Protect the level of quality,
- Embrace change,
- Keep teams stable; do not add people to a team in order to try to
go faster
- Accept that the customer doesn't need everything
Risk theme purpose + tailored to agile
The purpose of the risk theme is to identify, assess and control
uncertainty and as a result, improve the ability of the project to
succeed

In prince2/agile, risks are reduced by iterative and incremental
delivery and by daily stand-up meetings
Change theme purpose + tailored to agile
To identify, assess and control any potential and approved changes to
the baseline
Prince2 Agile: control significant changes, embrace the others
Plans theme purpose + tailored to agile
Recommends different levels of plan to facilitate communication and
control from the differing perspectives of the project organization
Plans enable the business case to be realized

Prince2 Agile: Empiricism has many advantages, and to use PRINCE2 in
an Agile environment this needs to be fully understood and embraced.
PRINCE2 plans need an end date to justify and authorize the plans, to
have a baseline for progress and to show that the Minimal Viable
Product (MVP) is created in time.
Organization theme purpose

, Defines the project organization structure and roles
Defines the approach to communicating and engaging with stakeholders
Prince2 Agile: enable self-organization by management by exception
Scrum Master
Coach or facilitator, who serves the product owner, development team,
and the organization
Project Product Description
Describes what the projet has to produce to obtain customer
acceptance
Issue Report
A relevant event that has happened, was not planned and requires
management action. It could be a problem, benefit, query, concern,
change request or risk that has occurred.
7 Principles
Continued Business Justification,
Learn from Experience,
Define Roles and Responsibilities,
Manage by Stages,
Manage by Exception,
Focus on Products,
Taylor to the Environment
7 Processes
Starting Up a Project
Initiating a Project
Directing a Project
Controlling a Stage
Managing Product Delivery
Managing Stage Boundaries
Closing a Project
7 Themes
Business Case,
Organisation,
Quality,
Plans,
Risks,
Change,
Progress
Starting Up a Project - process
Ensures that the prerequisites for initiating a project are in place
by answering the question: Do we have a viable and worthwhile project?
Initiating a Project - process
Establishes a solid foundations for the project and to enable the
organization to understand the work that needs to be done including a
plan
$10.49
Get access to the full document:

100% satisfaction guarantee
Immediately available after payment
Both online and in PDF
No strings attached

Get to know the seller
Seller avatar
munyuabeatrice92

Get to know the seller

Seller avatar
munyuabeatrice92 K
Follow You need to be logged in order to follow users or courses
Sold
1
Member since
1 year
Number of followers
1
Documents
347
Last sold
1 year ago

0.0

0 reviews

5
0
4
0
3
0
2
0
1
0

Recently viewed by you

Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their tests and reviewed by others who've used these notes.

Didn't get what you expected? Choose another document

No worries! You can instantly pick a different document that better fits what you're looking for.

Pay as you like, start learning right away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and aced it. It really can be that simple.”

Alisha Student

Frequently asked questions