What should a business case include? - correct answer B - Background
O - Options
B- Benefits
CA - Commercial Aspects
R - Risks
T - Timescales
What are the 5 aspects of the PRAM? - correct answer Initiate
Identify
Assess
Plan responses
Implement responses
What are the 5 phases in the extended project life cycle? - correct answer Concept
Definition
Development
Handover and Closure
Operations
Who are potential stakeholders within a project? - correct answer Project Sponsor
Project Team
Users
Suppliers
Customers
Senior Management
, What are the 5 steps within the information management process? - correct answer Collection
Storage
Dissemination
Archiving
Destruction
What are the steps of the requirements management process? - correct answer Capture
Analyse
Justify
Baseline
What are the steps of the change control process? - correct answer - Submit Change Request
- Review viability of taking request further
- Assessment of feasibility and impact of the proposed change
- Decision
What are potential sources of change? - correct answer Internal:
- Technical Error
- Incorrect Estimate
- Resourcing Issues
External:
- Business Justification
- Requirements change
- Technology/Market Shift
What is the requirements model? - correct answer Business Need (Why)
Features (How)