PRINCE2 FOUNDATION Test 2 Questions And Answers
PRINCE2 FOUNDATION Test 2 Questions And Answers Which is recommended as a possible risk for an opportunity? - ANS Exploit What are the three recommended types of issue? - ANS Off-specification, request for change and problem/concern Which project management product is the project diary for the Project Manager and is used to record problems/concerns to be handled informally? - ANS Daily Log What is the purpose of a Checkpoint Report? - ANS Updates the project Manager on the status of a Work Package