CON 2370 SIMPLIFIED ACQUISITION PROCEDURES TAKE 14 QUESTIONS WITH CORRECT AND DETAILED ANSWERS LATEST EXAM Only one quote was received in response to your competitive solicitation for Government-unique tool kits that utilized the lowest price technically acceptable source selection process. The quote, from Tool Warehouse, was determined to be technically acceptable and was for a price of $124,500. Which one of the following statements about the award decision is correct? - ANSWERNot - The requirement must be reconsolidated in order to obtain competition.

Show more Read less
Institution
Course









Whoops! We can’t load your doc right now. Try again or contact support.

Written for

Course

Document information

Uploaded on
November 28, 2023
Number of pages
14
Written in
2023/2024
Type
Exam (elaborations)
Contains
Questions & answers

Subjects

Content preview

CON 2370 SIMPLIFIED ACQUISITION
PROCEDURES TAKE 14 QUESTIONS WITH
CORRECT AND DETAILED ANSWERS
LATEST EXAM
Only one quote was received in response to your competitive solicitation for
Government-unique tool kits that utilized the lowest price technically acceptable source
selection process. The quote, from Tool Warehouse, was determined to be technically
acceptable and was for a price of $124,500.

Which one of the following statements about the award decision is correct? -
ANSWERNot - The requirement must be reconsolidated in order to obtain competition.

Six quotes were received in response to your solicitation for new office equipment that
utilized the lowest price technically acceptable source selection process. The quotes
submitted by vendors A, B, and D were determined to be technically acceptable.
Vendor A quoted a price of $146,500;Vendor B quoted a price of $128,250; and Vendor
D quoted a price of $132,800.

Which one of the following statements about the award decision is correct? - ANSWER
Vendor B is the apparent awardee and price reasonableness would be based on
competition

Take 13 - ANSWERtake 13

Three quotes were received in response to your solicitation for training services.
Evaluation was based on a tradeoff between price and past performance. The assigned
past performance ratings and quoted prices were as follows:
Vendor A - Unacceptable, $216,150;
Vendor B - Acceptable, $248,500; and
Vendor C - Outstanding, $237,200.

Which one of the following statements about the award decision is correct? – ANSWER
Not - Vendor B is the apparent awardee and price reasonableness could be based on
any reasonable basis

Not - Vendor A is the apparent awardee and price reasonableness would be based on
competition

Vendor c

Which one of the following is correct regarding documenting the award of a buy using
SAP? - ANSWERNot - Award documentation must be extensive and detailed

Not - Records of oral price quotations are not required

, Not - Records of oral price quotations must be established to clearly reflect the
appropriateness of the award decision.

Not - Comparison of competitive quotes or offers is the least preferred method for
determining price reasonableness.

Which one of the following is NOT a mandatory Government source for satisfying a
supply requirement? - ANSWERNot - Excess from other agencies

Not - Wholesale supply sources

Commercial sources

Which one of the following is NOT correct regarding documenting the award of a buy
using SAP? - ANSWER19. Maybe not - Records of oral price quotations must be
established to clearly reflect the appropriateness of the award decision.

Not - Price reasonableness should be based on competitive quotes or offers whenever
possible.

Not - A statement of price reasonableness is not required when only one quote or offer
is received.

Which one of the following is NOT one of the first steps taken when quotations are
received in response to a solicitation using SAP? - ANSWERNot - Reviewing the
quotations for responsibility

Not - Reviewing electronic and digital submission to ensure they are readable

Not - Ranking the quotations by technical acceptability

Ensuring quotations are marked with the date and time they were received

Documenting the quotations with the date and time they were received

Not - Safeguarding proprietary and sensitive information in the quotations form improper
release.

Which one of the following mandatory Government sources is the first priority for
satisfying a requirement for services? - ANSWERNot - Federal Prison Industries

Not - The Procurement List maintained by The Committee for Purchase From People
Who Are Blind or Severely Disabled

Inventories of the requiring agencies
$19.49
Get access to the full document:

100% satisfaction guarantee
Immediately available after payment
Both online and in PDF
No strings attached

Get to know the seller
Seller avatar
mutheewinnie900

Get to know the seller

Seller avatar
mutheewinnie900 Johns Hopkins University
Follow You need to be logged in order to follow users or courses
Sold
0
Member since
2 year
Number of followers
0
Documents
32
Last sold
-

0.0

0 reviews

5
0
4
0
3
0
2
0
1
0

Recently viewed by you

Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their tests and reviewed by others who've used these notes.

Didn't get what you expected? Choose another document

No worries! You can instantly pick a different document that better fits what you're looking for.

Pay as you like, start learning right away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and aced it. It really can be that simple.”

Alisha Student

Frequently asked questions