CAPM Practice Test Questions with correct answers
A. Assumptions CM 4.7.2 PMBOK 5.3.3.1 Correct Answer-Project planning is ongoing as the team analyzes how long it will take to process both a new order and a change order through the new call center. This analysis helps them determine how many employees must be working in the car center based on anticipated customer volume. This is an example of what? A. Determine budget CM 7.13; PMBOK 7.3 Correct Answer-The project manager and her team are involved in establishing the cost of the project and applying them to the schedule in order to determine when these cost will occur. During the project during which process does this occur? D. initiating, planning, executing, monitoring and controlling, closing (IPEM&CC) CM 3.3.1; PMBOK 1.5.1 Correct Answer-During project performance, the team will focus on the Project Life Cycle and the project management life cycle. What are the five phases of a project management life cycle (PMLC)? A. Risk Seeker CM 11.2.7; PMBOK 11 INTRO Correct Answer-The project manager is considering quitting his job to develop a book and supporting products for the project management professional exam, and idea he created outside his job. If it sells well, he plans to start his own company and sell the products full-time. What characteristics is he showing towards risk? D. all of the above (Interactive, Push, Pull) CM 10.3.5; PMBOK 10.1.2.4 Correct Answer-Which of the following communication methods should be applied to managing project engagement?
Written for
- Institution
- CAPM - Certified Associate in Project Management
- Course
- CAPM - Certified Associate in Project Management
Document information
- Uploaded on
- October 10, 2023
- Number of pages
- 5
- Written in
- 2023/2024
- Type
- Exam (elaborations)
- Contains
- Questions & answers
Subjects
-
capm practice test questions with correct answers
Also available in package deal