NERC SOS Pre-Assessment Rated 100% Correct!!
What are three primary AGC control models? - Tie-Line Bias, Constant Frequency, Constant Net Interchange When a balancing Authority's ACE is zero, what is true? - The BA load-interchange-generation balancing while supporting Interconnection Frequency In a 3-phase AC generator... - Each phase is physically offset by 120 degrees Inductance is a property of an electric circuit that opposes the change in ___ - current What three values are included in OHM's Law? - Volts, Amps, impedance You dispatch a field crew to a substation to help determine the reason for a transmission line trip. What is the first thing you are going to ask them to do? - Read Targets When energizing a long, HV transmission line from one end, what would you expect to see on the open end of the line? - Higher Voltage than the closed end What is inadvertent? - The difference between actual and scheduled interchange What is a balancing area between the source and sink balancing areas called? - Intermediary Balancing Area What does AGC stand for? - Automatic Generation Control When implementing an interchange schedule, what tool is used to document and distribute the information associated with the transaction? - E-TagIn order for a generator to produce megawatts, it must have a _____ - torque Angle On an electric generator, what does the term "Ramp Rate" Mean? - The generators ability to increase or decrease MW output over a given period of time Low Voltage is an indication there is ______ - A Deficiency in reactive power
Written for
- Institution
- NERC SOS
- Course
- NERC SOS
Document information
- Uploaded on
- September 29, 2023
- Number of pages
- 9
- Written in
- 2023/2024
- Type
- Exam (elaborations)
- Contains
- Questions & answers
Subjects
Also available in package deal