CDT EXAM QUESTIONS AND ANSWERS (DISTINCTION GUARANTEED)-DUE DATE; 5TH OCTOBER 2023.
CDT EXAM QUESTIONS AND ANSWERS (DISTINCTION GUARANTEED)-DUE DATE; 5TH OCTOBER 2023. Select the entity which is generally assigned the following duties and responsibilities by the Conditions of the Contract: Protection of job site workers and stored materials. A - Architect/Engineer B - Owner C - Contractor D - Varies, as stated in the Supplementary Conditions E - None of the above Reference: PDPG 5.4.1.7 and PDPG 15.12.11; EJCDC C-700 Paras. 7.12 through 7.15; AIA A201 Sections 10.1, 10.2, and 10.4. Also see CCAPG 6.8; CCPG 9.14.-CORRECT ANSWER-Answer: C - Contractor. Safety provisions in both EJCDC and AIA documents clearly make safety and protection of persons and property at the construction Site the sole responsibility of the Contractor. Select the entity which is generally assigned the following duties and responsibilities by the Conditions of the Contract: Resolution of claims. A - Owner B - Contractor C - Varies, as stated in the Supplementary Conditions D - Initial Decision Maker Reference: PDPG 15.15.3; AIA A201 Sections 1.1.8 and 15.2. Also see CCAPG Chapter 10 (particularly CCAPG 10.3)-CORRECT ANSWER-Answer: D - Initial Decision Maker. The Initial Decision Maker is an entity that exists only in AIA documents and is not used in EJCDC documents. In AIA documents, when an entity other than the Architect is named as the Initial Decision Maker, said entity is identified in AIA A101 (Owner-Contractor Agreement) Section 6.1. In actual practice with AIA documents, the Initial Decision Maker is typically the Architect, but may be a third party considered to be neutral. select the entity which is generally assigned the following duties and responsibilities by the Conditions of the Contract: Paying taxes for the Work. A - Architect/Engineer B - Owner C - Contractor D - Varies, as stated in the Supplementary Conditions E - None of the above Reference: EJCDC C-700 Para. 7.09; AIA A201 Section 3.6; PDPG 13.6.4.4 among others. Also see CCAPG 3.1.4.-CORRECT ANSWER-Answer: C - Contractor. Taxes are part of the cost of construction for which the Contractor is responsible under the terms of the Contract Documents. For public work, where public owners are often exempt from certain sales and ues taxes on materials and equipment to be incorporated into the construction, typically an associated Supplementary Conditions provision is necessary to properly indicate the statutory requirements for taxes, which can vary significantly from state to state. select the entity which is generally assigned the following duties and responsibilities by the Conditions of the Contract: Right to stop work, if non-conforming Work fails to be corrected. A - Architect/Engineer B - Owner C - Contractor D - Varies, as stated in the Supplementary Conditions E - None of the above Reference: PDPG 15.9.5.1; EJCDC C-700 Para 14.06; AIA A201 Sections 2.4, 14.2 and 14.3. Also see CCAPG 2.1; CCAPG 6.2.2;-CORRECT ANSWER-Answer: B - Owner. Standard contract documents such as EJCDC's and AIA's reserve to the Owner sole right to stop or suspend the Work if the Work does not comply with the Contract Documents. This right is solely the Owner's, and should never be assumed by or delegated to the A/E (or a construction manager), because stopping the Work is an extreme action that almost always results in a delay Claim from the Contractor for additional time and compensation. In EJCDC and AIA documents, the A/E does not have authority to stop or suspend the Work for non-conformance because issuing such an order is tantamount to opening the Owner's checkbook and handing out money. Which of the following is part of the construction documents but not part of the Contract Documents? A - Procurement Forms B - Agreement C - Performance Bond D - General Conditions E - Addenda F - Contract Modifications Reference: PDPG 12.1 and PDPG 12.2; EJCDC C-700 Paras. 1.01.A.6 and 7; AIA A201 Section 1.1.1; and "The Diagram". Also see CCAPG 1.3.1; CCAPG 8.2. Also see CSPG Chapter 9-CORRECT ANSWER-Answer: A - Procurement Forms (also known as the Bid Form and its supplements). The Procurement (Bidding) Requirements, which include the advertisement or invitation to bid, instructions to bidders/proposers, bid form, bid bond form (if any), qualifications statement (if any), and other bid form supplements (if any), are required only for the Project's procurement (bidding/pricing) stage and therefore are not typically considered to be "Contract Documents" (remember: "Contract Documents" exist only after the parties have both signed the Owner-Contractor Agreement). If you are still having trouble wrapping your mind around this, consider that the Procurement (Bidding) requirements are necessary for, and apply only through, the procurement (bidding) stage—they address matters only until the Owner-Contractor Agreement is signed and the Contract becomes effective. Therefore, the Procurement (Bidding) Requirements are not necessary once the Contract
Written for
- Institution
- CDT
- Course
- CDT
Document information
- Uploaded on
- September 29, 2023
- Number of pages
- 55
- Written in
- 2023/2024
- Type
- Exam (elaborations)
- Contains
- Questions & answers
Subjects
-
select the entity which is generally assigned the
-
select the entity which is generally assigned the
-
which of the following is part of the construction
-
which of the following is true regarding conditio
Also available in package deal