This type of closure occurs when the project may never seem to end. At some point
the review group should recommend methods for bringing final closure to this type
of project. This is considered ___________ closure.
a. normal
b. premature
c. perpetual
d. changed priority
e. failed project
Clear my choice
Question 2
Not yet answered
Marked out of 1.00
It can be a significant challenge to keep the project team ___________ as the project
nears completion.
a. focused
b. working
c. energetic
d. together
e. performing
Clear my choice