Question 1
True or False? Earned values associate a weight to a task to help identify importance during system
test tracking.
Flase
2.
Question 2
Given the following tasks and earned values, is the project above, on, or below budget?
1A 30 2A 10
1B 50 2B 20
1C 20
Week 1 To be Completed: 1A, 1B, 2A
Week 1 Actually Completed: 1A, 1B, 1C at a cost of 90
Below budget
3.
Question 3
Which of the following is not a process improvement phase?
point
Correct
4.
Question 4
True or False? GQM advocates that a project should collect as many metrics as possible.
Flase
5.
Question 5
True or False? As part of the outsourcing contract, an organization might require that particular
testing processes be followed.
True
6.
Question 6
Which of the following is not a component of a statement of work?
Bugeted cost of work performed
This study source was downloaded by 100000850872992 from CourseHero.com on 04-04-2023 01:42:15 GMT -05:00
https://www.coursehero.com/file/111389146/week-8-quiz-pdf/