Your installation is refurbishing an existing PES facility built in 1968. Do you need to
complete an ESSP? - Correct answer-Yes, and it requires DDESB approval.
As distance from the potential explosion site decreases, the potential for damage to an
exposed site from an explosion.... - Correct answer-increases.
Your installation is increasing the NEW for a storage site built in 1969 and storing a
hazard division that was not previously approved for that location. Do you need to
complete an ESSP? - Correct answer-Yes, and it requires DDESB approval.
Intraline distance (ILD) is the minimum distance permitted between... - Correct answer-
two operating buildings.
The purpose of an ESSP is to ensure safety, provide specifications, and... - Correct
answer-establish limits.
You must submit an ESSP for DDESB approval if the installation is... - Correct answer-
building an ES within an existing ESQD arc.
Failing to submit a successful ESSP may result in... - Correct answer-reduced
operational capacity.
Which are the phases of the ESSP process in order? - Correct answer-Development
and Evaluation, Submission, DDESB Review, and Implementation.
The Expedited Approval Request must... - Correct answer-explain why an expedited
approval is required.
Which part of the ESSP package contains background information, site location, and
the reason for the ESSP submission? - Correct answer-ESSP narrative
Which ESSP category addresses facilities and operations that do not completely
conform to deterministic QD criteria or meet the risk-based criteria in DESR 6055.09
Edition 1? - Correct answer-HSP
Which is NOT a common mistake when submitting an ESSP? - Correct answer-Sending
the ESSP to USATCES