100% satisfaction guarantee Immediately available after payment Both online and in PDF No strings attached 4.6 TrustPilot
logo-home
Exam (elaborations)

Project Management A Systems Approach to Planning, Scheduling, and Controlling, Kerzner - Exam Preparation Test Bank (Downloadable Doc)

Rating
-
Sold
-
Pages
66
Grade
A+
Uploaded on
05-07-2022
Written in
2021/2022

Description: Test Bank for Project Management A Systems Approach to Planning, Scheduling, and Controlling, Kerzner, 11e prepares you efficiently for your upcoming exams. It contains practice test questions tailored for your textbook. Project Management A Systems Approach to Planning, Scheduling, and Controlling, Kerzner, 11e Test bank allow you to access quizzes and multiple choice questions written specifically for your course. The test bank will most likely cover the entire textbook. Thus, you will get exams for each chapter in the book. You can still take advatange of the test bank even though you are using newer or older edition of the book. Simply because the textbook content will not significantly change in ne editions. In fact, some test banks remain identical for all editions. Disclaimer: We take copyright seriously. While we do our best to adhere to all IP laws mistakes sometimes happen. Therefore, if you believe the document contains infringed material, please get in touch with us and provide your electronic signature. and upon verification the doc will be deleted.

Show more Read less











Whoops! We can’t load your doc right now. Try again or contact support.

Document information

Uploaded on
July 5, 2022
Number of pages
66
Written in
2021/2022
Type
Exam (elaborations)
Contains
Questions & answers

Content preview

CHAPTER 1: OVERVIEW


(E) 1. In today’s market, which of the following industries appears to have a need for
project management?
A. Aerospace & defense
B. Construction
C. Information systems
* D. All industries have a need for project management


(M) 2. Which of the following is not one of the PMBOK  Guide’s five process
groups?
* A. Feasibility studies
B. Planning
C. Execution
D. Closure


(E) 3. Which of the following is normally not one of the traditional components of
the triple constraint?
A. Within time
B. Within cost
C. Within performance (Scope, technology or quality)
* D. Accepted by the customer


(M) 4. Which of the following is a potential benefit of using project management?
A. Maximization of continuous reporting
B. No need for identification of functional responsibilities
* C. Identification of time limits for scheduling
D. No need for a project management methodology


(E) 5. Which of the following functions of classical management is generally not
performed by the project manager?
A. Planning
B. Organizing
* C. Staffing
D. Controlling


(M) 6. Which of the following three types of deliverables discussed in the book would
be used to classify the final report that must be presented to the customer at the
end of the project?
A. Hardware deliverables

, * B. Software deliverables
C. Interim deliverables
D. Validation deliverables


(E) 7. Which of the following is not an organizational stakeholder?
A. Executive officers
B. Unions
C. Employees
* D. Customers


(E) 8. Which of the following is not a product/market stakeholder?
* A. Creditors
B. Customers
C. Suppliers
D. Governments


(E) 9. Which of the following is not a capital market stakeholder?
A. Banks
* B. Unions
C. Shareholders
D. Creditors


(M) 10. Which of the following is directly controlled by the project manager?
A. Money
B. Manpower
C. Information / technology
* D. None of the above


(H) 11. Which of the following is reflective of the changes in project management
according to Dr. Thamhain?
A. Moving from dynamic to linear processes
* B. Moving toward full utilization of information technology
C. Moving away from the use of an enterprise-wide methodology
D. Moving from effectiveness to efficiency


(E) 12. Successful project management requires a good daily working relationship
between project and line managers.
* A. True
B. False

,(E) 13. Successful project management does not require that people understand how to
report to multiple bosses.
A. True
* B. False


(E) 14. The project manager’s role as an integrator of activities does not include
integration of activities necessary to:
A. Develop the plan
B. Execute the plan
C. Make changes to the plan
* D. All of above are PM roles


(M) 15. The PM’s role with regard to interface management does not include
interfacing:
A. Within the project team
B. Between the project team and functional organizations
C. Between the project team and senior management
* D. Between senior management and various external stakeholders


(H) 16. Which of the following is the role of the PM rather than the role of the
functional manager?
* A. What work will be done
B. How the work will be done
C. Who will do it
D. Where it will be done


(E) 17. Which of the following problems affects the functional manager’s ability to
staff and support a project during execution?
A. Limited availability of resources
B. Predetermined deadlines
C. Unscheduled changes to the project plan
* D. all of the above


(H) 18. What type of project manager would have employees (i.e. team members) that
report directly to the project manager full-time for the duration of the project?
A. Lightweight team leader
B. Heavyweight team leader
* C. Tiger team leader
D. Leopard Team leader

, (H) 19. When team members take direction from both the project and line managers,
the type of project manager is usually
A. Lightweight team leader
* B. Heavyweight team leader
C. Tiger team leader
D. Leopard team leader


(H) 20. On a project headed up by a lightweight project manager, employees have their
performance reviews made by:
* A. Line managers only
B. Line managers with input from the project managers
C. Concurrence jointly by project managers and line managers
D. Project managers only


(H) 21. Which of the following is normally not part of a team member’s role?
A. Accepting responsibility for a deliverable
* B. Sharing information with the sponsor
C. Sharing information with the team
D. Completing the work at the earliest possible time.


(M) 22. In which life cycle phase do project sponsors become most actively involved in
the project?
* A. Initiation
B. Execution
C. Monitor and control
D. Closure


(M) 23. Which of the following is not part of the project sponsor’s role?
A. Conflict resolution
B. Priority-setting
* C. Selection of project team members
D. Monitoring performance at a high level


(M) 24. Project sponsorship almost always resides at the executive levels
A. True
* B. False


(M) 25. Which of the following promises can project managers make to functional
employees assigned to a project?

Get to know the seller

Seller avatar
Reputation scores are based on the amount of documents a seller has sold for a fee and the reviews they have received for those documents. There are three levels: Bronze, Silver and Gold. The better the reputation, the more your can rely on the quality of the sellers work.
tb4u City University New York
View profile
Follow You need to be logged in order to follow users or courses
Sold
975
Member since
3 year
Number of followers
776
Documents
2371
Last sold
4 days ago

4.0

159 reviews

5
88
4
27
3
19
2
6
1
19

Recently viewed by you

Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their tests and reviewed by others who've used these notes.

Didn't get what you expected? Choose another document

No worries! You can instantly pick a different document that better fits what you're looking for.

Pay as you like, start learning right away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and aced it. It really can be that simple.”

Alisha Student

Frequently asked questions