A milestone task on the critical path has been completed.
which of the following should the project manager notify?
A owner of predecessor task
B project team
C project sponsor
D project steering committee correct answer- C
During a project assessment, a project manager
determines the initial project cost estimates were
incorrect oh, and there is not enough budget left,
including reserves, to complete the project.
Which of the following actions should the project
manager take?
A alert the project sponsor of the situation
B contact the customer and request more funding
C announce the project will end due to lack of funds
D attempt to save money in downstream activities
correct answer- A
Which of the following is the primary purpose of an MOA
or an mou?
A State expectations of all signatory parties to reduce
potential misunderstandings
,B facilitate potential legal action and resulting
remediation if one of the signatory parties violate any
terms
C enumerate a detail code of conduct for all employees,
contractors, and subcontractors participating in the
program.
D provide transparency to competitors regarding all
signatory parties correct answer- A
two team members have concluded that documentation
is not required due to the size of the current project. The
project manager has encouraged them to align strictly
with the process.
which of the following conflict resolution techniques has
the project manager utilized?
A smoothing
B forcing
C compromising
D avoiding correct answer- B
The client accepts the critical design review.
which of the following meetings should be held to move
to the next step in the project?
A execution
B kickoff
C closure
D planning correct answer- B
,A project manager is working on the project charter.
Which of the following phases does this describe?
A initiation
B planning
C execution
D closing correct answer- A
A project in the execution phase is over budget, and tasks
on the critical path are on schedule.
Which of the following should the project manager do
next?
A update the project management plan
B issue a change request
C revise the project charter
D evaluate the impact to the baseline correct answer- D
Several team members report that meeting objectives
are not being met.
which of the following documents would a project
manager free to make team meetings more effective?
Choose two
1 create an s o w prior to each meeting and adhere to it
2 create a meeting agenda prior to each meeting and
adhere to it
3 create a lessons learned list prior to each meeting and
adhere to it
, 4 create a project charter prior to each meeting and
adhere to it
5 create an action item list during the meeting and
adhere to it
6 create a corrective action plan prior to each meeting
and adhere to it
7 create a WBS prior to each meeting and adhere to it
A 2,5
B 1,4 correct answer- A
Which of the following documents should be used prior to
high-level recording to key stakeholders?
A dashboard
B communication plan
C statement of work
D project charter correct answer- A
A new project charter is being drafted.
which of the following would be the best source for the
high-level project requirements?
A sponsor
B project manager
C project management office
D project team correct answer- A
Which of the following project document should be used
to record the occurrence of an unplanned event?
A action log
B risk log