11/11/21
Read the assignment and the scenario and saw what to do for the
assignment.
12/11/21
I started the introduction for the assignment and listed down the
problems and looked at the scope of the system. I also did the key
driver tables and started solution 1.
18/11/21
Learnt how to use Microsoft project and did an example of a project plan
which will help me do one for my assignment.
19/11/21
Aim is to finish solution 1 and 2 tables which I did.
26/11/21
Started on the evaluation of what solution to use and costs, benefits,
legal, security and usability of the solution and how it will solve the
problems.
2/12/21
Analysed the risks and issues that may happen in the project and what
the impact of the risk and issues are and then how it can be minimised
or avoided.
3/12/21
Finish doing the risks and issues table for the project.
11/11/21
Read the assignment and the scenario and saw what to do for the
assignment.
12/11/21
I started the introduction for the assignment and listed down the
problems and looked at the scope of the system. I also did the key
driver tables and started solution 1.
18/11/21
Learnt how to use Microsoft project and did an example of a project plan
which will help me do one for my assignment.
19/11/21
Aim is to finish solution 1 and 2 tables which I did.
26/11/21
Started on the evaluation of what solution to use and costs, benefits,
legal, security and usability of the solution and how it will solve the
problems.
2/12/21
Analysed the risks and issues that may happen in the project and what
the impact of the risk and issues are and then how it can be minimised
or avoided.
3/12/21
Finish doing the risks and issues table for the project.