✔✔You know that you are sensitive to amines but not polyamides. What document
would you review prior to arriving at the jobsite?
A. Inspection Plan
B. Coating application guide
C. The contractor's contract
D. Safety Data Sheet - ✔✔D. Safety Data Sheet
✔✔You are reviewing the documentation for a tank coating project, and you notice there
is a conflict between the specification and the PDS and the required DFT of the primer.
The owner is not reachable for clarification. What should you do?
A. Follow the PDS
B. Follow the specification
C. Shut down the job
D. The contractor will decide how to proceed - ✔✔B. Follow the specification
✔✔When communicating with other team members on the job-site , the inspector
should be mindful of their __________? (Select all that apply)
A. Body language
B. Their physical appearance
C. Choice of words
D. Tone of voice - ✔✔A. Body language
C. Choice of words
D. Tone of voice
✔✔When a conflict occurs on a coating project, the inspector's first course of action is
to________________?
A. Call the supervisors to obtain support for you position
B. Call the owner to obtain support for you position
C. State your position as the inspector, and win the argument
D. Actively listen and try to understand the positions of the other party - ✔✔D. Actively
listen and try to understand the positions of the other party
✔✔A typical daily report should include which of the following? (Select all that apply)
A. Description of manpower and equipment used by the contractor
B. Explanation of work stoppages
C. Evaluation of the contractor's work
D. Environmental conditions
E. Safety concerns - ✔✔A. Description of manpower and equipment used by the
contractor
B. Explanation of work stoppages
D. Environmental conditions
E. Safety concerns
, ✔✔Before the start of the Pre Job Conference the inspector should obtain a copy of,
read, and understand which of the following? (Select all that apply)
A. Specification
B. Standard
C. Product Data Sheets
D. Safety Data Sheets - ✔✔A. Specification
B. Standard
C. Product Data Sheets
D. Safety Data Sheets
✔✔What are the inspector's goals during the Pre-Job Conference? (Select all that
apply)
A. Understand the process for addressing deviations and conflicts
B. To chair the meeting to ensure that their agenda items are addressed
C. Obtain a clear understanding of the authority, responsibilities, and deliverables
D. Make a good first impression and build positive working relationships - ✔✔A.
Understand the process for addressing deviations and conflicts
C. Obtain a clear understanding of the authority, responsibilities, and deliverables
D. Make a good first impression and build positive working relationships
✔✔Which of the following team members would not typically attend the Pre-Job
Conference?
A. Inspector
B. The Application and Blasting Teams
C. Contractor
D. Asset Owner
E. Specification Writer - ✔✔B. The Application and Blasting Teams
✔✔When completed thoroughly, inspection documentation can _____________?
(Select all that apply)
A. Contribute to the quality control of a project
B. Help to protect the inspector from negligence accusations
C. Cause confusion
D. Help to establish a maintenance program
E. Help to guide future projects - ✔✔A. Contribute to the quality control of a project
B. Help to protect the inspector from negligence accusations
D. Help to establish a maintenance program
E. Help to guide future projects
✔✔Which of the following documents, is not routinely submitted to the client?
A. Daily Report
B. Non-Conference Report
C. Logbook
D. Instrument Calibration Report - ✔✔C. Logbook