The purpose of Construction Quality Management is to: - (answer)Achieve the quality established by
properly developed requirements through the combined responsibility, but seperate efforts of
contractpr smd government personnel.
Construction Quality Management is the performance of tasks, which ensure that construction is
performed. - (answer)According to plans and specifications, on time, within a defined budget and a safe
work environment.
Partnering relationships are based upon: - (answer)Building trust and dedication to common goals
It is the responsibility of Quality Assurance Personnel to: - (answer)Periodically verify that the
contractors system of control is working effectively.
An effective contractor quality control program will: - (answer)Be an incentive for work to be done
correctly the first time resulting in earlier completion, reduced field overhead costs, and greater profits.
The success or failure of all contractors is based upon: - (answer)The ability to control costs, finance
work, estimate jobs, schedule the work, and maintain effective quality control.
Quality Assurance Personnel have the responsibility to: - (answer)Require contractors to maintain the
quality specified in the plans and specifications.
Inspection is: - (answer)The process by which ongoing and completed work is examined
During the punch-out inspection of a project: - (answer)Quality Assurance Personnel must assure that
the contractor prepares a punch-list and makes corrections.
If there is a disagreement whether the contractors work complies with the contract: - (answer)The
government makes the final determination
New Version!
The purpose of Construction Quality Management is to: - (answer)Achieve the quality established by
properly developed requirements through the combined responsibility, but seperate efforts of
contractpr smd government personnel.
Construction Quality Management is the performance of tasks, which ensure that construction is
performed. - (answer)According to plans and specifications, on time, within a defined budget and a safe
work environment.
Partnering relationships are based upon: - (answer)Building trust and dedication to common goals
It is the responsibility of Quality Assurance Personnel to: - (answer)Periodically verify that the
contractors system of control is working effectively.
An effective contractor quality control program will: - (answer)Be an incentive for work to be done
correctly the first time resulting in earlier completion, reduced field overhead costs, and greater profits.
The success or failure of all contractors is based upon: - (answer)The ability to control costs, finance
work, estimate jobs, schedule the work, and maintain effective quality control.
Quality Assurance Personnel have the responsibility to: - (answer)Require contractors to maintain the
quality specified in the plans and specifications.
Inspection is: - (answer)The process by which ongoing and completed work is examined
During the punch-out inspection of a project: - (answer)Quality Assurance Personnel must assure that
the contractor prepares a punch-list and makes corrections.
If there is a disagreement whether the contractors work complies with the contract: - (answer)The
government makes the final determination