(BARROWS)QUESTIONS AND ANSWERS
(T/F) If owner is looking to achieve an iconic design for their project,
using the design/build project delivery method is their best option -
correct answer ✅False
(T/F) A general contractor that utilizes a design-bid-build project
delivery method typically accepts more risk then a contractor that
utilizes a design-build project delivery method -
correct answer ✅False
(T/F) When an owner is using the construction manager not at risk
project delivery method the general contractor won't typically get
involved until after the pre construction process is complete -
correct answer ✅False
(T/F) Once an owner awards a project to a general contractor, the
contractor is guaranteed to make the original amount of profit they
determined on bid day -
correct answer ✅False
(T/F) An addendum is a change to the bidding documents that
occurs after the owner enters into a contract with the general
contractor -
correct answer ✅False
,CNST 379 - FINAL EXAM
(BARROWS)QUESTIONS AND ANSWERS
(T/F) An RFQ is a document issued by a buyer of services to sellers
of services, requesting documentation of their general
qualifications an experience, to determine whether such sellers are
qualified to provide the services required by the buyer -
correct answer ✅True
(T/F) A verbal response from the architect or owner to a request for
information from a contractor during a pre bid site visit is legally
binding -
correct answer ✅False
(T/F) The GMP contract type is most often used with the design-bid-
build project delivery method -
correct answer ✅False
GMP is a term used when discussing contract types. GMP stands for
-
correct answer ✅Guaranteed Maximum Price
The project delivery method in which the major members of a
project team enter into a multiparty agreement, place their profit
,CNST 379 - FINAL EXAM
(BARROWS)QUESTIONS AND ANSWERS
into a risk pool, and share equally in the risks and rewards of the
project is called -
correct answer ✅IPD
What is the name of a spreadsheet used to compile all the costs of
the bid for a construction project? (Including general conditions,
direct costs, indirect costs, fee, OH, insurance, etc) -
correct answer ✅Bid Tab
The project delivery method used most often for smaller, horizontal
construction projects is -
correct answer ✅dbb
the project delivery method used most for vertical construction
projects is -
correct answer ✅dbb
The most detailed and lowest level of a work breakdown structure
is broken down into separate -
correct answer ✅work packages
, CNST 379 - FINAL EXAM
(BARROWS)QUESTIONS AND ANSWERS
CD, DD, and SD are acronyms that describes the level of design of a
set of project documents. Which phase shows the most amount of
information? -
correct answer ✅CD
CD stands for -
correct answer ✅Construction Documents
DD stands for -
correct answer ✅Design documents
SD stands for -
correct answer ✅Schematic design
A construction contract type where are the quantities are provided
by the owner/engineer and the contractor only has to assign cost is
a ____________ contract type -
correct answer ✅Unit price
IPD is a project delivery method. IPD stands for -
correct answer ✅Integrated project delivery