Answers (Latest Update 2026)
UNL's new College of Engineering Building (Kiewit Hall) uses which
of the following project delivery methods?
a. CMar
b. design/build
c. IPD
d. P3
e. Design-Bid-Build -
correct answer ✅a. CMar
It is usually easy for a general contractor to obtain private bid
opportunities than it is to obtain public bid opportunities.
True or False -
correct answer ✅false
An RFP, will typically contain which of the following: (Select all that
apply)
-Type of owner contract to be used
-Anticipated cost and desired schedule
-Time and date of bid response
,CNST 379 Exam 1- Questions and
Answers (Latest Update 2026)
-Owner's contact information
-Type of project delivery method -
correct answer ✅all the above
The RFQ process, if utilized by and owner, is typically done in
advance of the RFP process.(T/F) -
correct answer ✅True
Which of the follow could be considered public owners? (Select all
that apply.) -
correct answer ✅-Lincoln Public Schools
-University of Nebraska - Lincoln
-Colorado Department of Transportation
A public owner can award a project to which ever firm they see fit.
(T/F) -
correct answer ✅false
RFP stands for request for ______________. (one word, lowercase,
singular) -
correct answer ✅Proposal
,CNST 379 Exam 1- Questions and
Answers (Latest Update 2026)
Which project delivery method typically results with the least risk
to the GC or Construction Manager?
a. public Private Partnership(P3)
b. CM at Risk
c. CM not at risk
d. Design- Bid- Build
e. Design/ Build
f. IPD -
correct answer ✅CM not at risk
Which project delivery method does the architect and engineer
contract directly with the general contractor/Construction
Manager?
a.Design-Bid-Build
b.CM at Risk
c. Design/Build
d.CM not at Risk
e. IPD -
correct answer ✅design/ Build
, CNST 379 Exam 1- Questions and
Answers (Latest Update 2026)
Which project delivery method typically results in the owner
receiving the lowest possible project cost?
a. Integrated Project Delivery (IPD)
b.CM not at Risk
c. CM at Risk
d. Design/Build
e. Design-Bid-Build -
correct answer ✅design-Bid-Build
Which project delivery methods (choose all that apply) does the
general contractor/construction manager enter into a contractual
agreement with the owner BEFORE the final contract amount has
been determined?
a. IPD
b. CM at Risk
c. CM not at risk
d. design/Build
c. Design-bid- build -
correct answer ✅IPD, CMar, CMR, design/build