Where is the best location for leveling a crane?
|\ |\ |\ |\ |\ |\ |\ |\
1. Carrier
|\
2. Upperworks
|\ |\
3. Cab
|\
4.Carbody - CORRECT ANSWERS ✔✔2. Upperworks |\ |\ |\ |\ |\
When determining the Agross load ~The best method is:
|\ |\ |\ |\ |\ |\ |\ |\
1. Guess the approximate load weight and add the
|\ |\ |\ |\ |\ |\ |\ |\ |\
rigging.
2. Get an accurate load weight and add the rigging.
|\ |\ |\ |\ |\ |\ |\ |\ |\
3. Guess the approximate load weight
|\ |\ |\ |\ |\ |\
4. Get an accurate load weight. - CORRECT ANSWERS
|\ |\ |\ |\ |\ |\ |\ |\ |\
✔✔2. Get an accurate load weight and add the rigging.
|\ |\ |\ |\ |\ |\ |\ |\ |\
By order of hitch strength, which is the correct answer?
|\ |\ |\ |\ |\ |\ |\ |\ |\
1. Vertical, Basket, Choker
|\ |\ |\
,2. Basket, Vertical, Choker
|\ |\ |\
3. Basket, Choker, Vertical
|\ |\ |\
4. Choker, Basket , Vertical - CORRECT ANSWERS ✔✔2.
|\ |\ |\ |\ |\ |\ |\ |\ |\
Basket, Vertical, Choker
|\ |\
What is the purpose of using Jib?
|\ |\ |\ |\ |\ |\
1. Increase load radius
|\ |\ |\ |\
2. Decrease load radius
|\ |\ |\
3. Increase height
|\ |\
4. Decrease height - CORRECT ANSWERS ✔✔3. Increase
|\ |\ |\ |\ |\ |\ |\ |\
height
When taking a side strain on a boom, what concerns the
|\ |\ |\ |\ |\ |\ |\ |\ |\ |\ |\
operator most? |\
1. No concern
|\ |\
2. Boom damage
|\ |\
3. Tipping
|\
4. Sheave damage - CORRECT ANSWERS ✔✔2. Boom
|\ |\ |\ |\ |\ |\ |\ |\
damage
, You should have at least how many wraps on a hoist
|\ |\ |\ |\ |\ |\ |\ |\ |\ |\ |\
drum?
1. 5
|\
2. 2
|\
3. 3
|\
4. 1 - CORRECT ANSWERS ✔✔2. 2
|\ |\ |\ |\ |\ |\
On a load chart, values above the bold line mean:
|\ |\ |\ |\ |\ |\ |\ |\ |\
1. Capacities based on tipping.
|\ |\ |\ |\
2. Capacities based on structural competence.
|\ |\ |\ |\ |\
3. Capacities should be reduced by 20%
|\ |\ |\ |\ |\ |\
4. On tire capacities - CORRECT ANSWERS ✔✔2.
|\ |\ |\ |\ |\ |\ |\ |\
Capacities based on structural competence. |\ |\ |\ |\
The primary purpose for a rooster sheave or auxiliary
|\ |\ |\ |\ |\ |\ |\ |\ |\
boom point sheave is to: |\ |\ |\ |\
1. Separate hoist lines
|\ |\ |\
2. Add height to the boom
|\ |\ |\ |\ |\
3. Increase load radius
|\ |\ |\ |\