Q1: What is the primary purpose of the Project Charter?
A: Formally authorize the project and define high-level objectives.
Rationale: It gives the project manager authority and establishes initial scope and stakeholders.
Q2: Which role is responsible for ensuring the project delivers the agreed scope?
A: Project Sponsor
Rationale: The sponsor champions the project and authorizes major decisions.
Q3: What process group occurs throughout the project?
A: Monitoring and Controlling
Rationale: This group continuously tracks, reviews, and regulates progress.
Q4: The Project Management Plan is developed during:
A: Planning
Rationale: It integrates subsidiary plans (scope, schedule, cost, risk, etc.).
Q5: The main output of Develop Project Charter is:
A: Project Charter
Rationale: Official authorization to proceed.
practice exam 2026
,2|Page
Q6: Integrated Change Control is performed in:
A: Monitoring and Controlling
Rationale: Ensures changes are evaluated before approval.
Q7: A stakeholder’s needs are documented in:
A: Requirements documentation
Rationale: Basis for defining scope and acceptance criteria.
Q8: Which technique prioritizes objectives by trade-off analysis?
A: Decision tree
Rationale: Supports evaluating risky decisions across outcomes.
Q9: The project manager’s primary responsibility is:
A: Delivering project objectives within constraints
Rationale: Balances scope, schedule, cost, quality, and stakeholders.
Q10: A benefit of strong project integration is:
A: Better alignment of objectives across teams
Rationale: Promotes unified execution and stakeholder satisfaction.
11–20: Scope Management
Q11: What establishes project boundaries and deliverables?
A: Scope Statement
Rationale: Describes what is included and excluded.
Q12: A WBS is used to:
A: Decompose work into manageable components
Rationale: Enables planning, estimating, and assignment of work.
practice exam 2026
,3|Page
Q13: WBS work packages should be:
A: Small enough to estimate duration and cost
Rationale: Helps improve accuracy.
Q14: The process to confirm deliverables with stakeholders is:
A: Validate Scope
Rationale: Ensures acceptance of completed work.
Q15: Scope creep occurs due to:
A: Uncontrolled changes
Rationale: Changes not properly managed lead to scope increase.
Q16: A detailed description of deliverables is found in:
A: Scope Baseline
Rationale: Includes scope statement, WBS, and WBS dictionary.
Q17: Change requests affecting scope must go through:
A: Integrated Change Control
Rationale: Ensures evaluation across all impact areas.
Q18: The process of subdividing project deliverables is:
A: Create WBS
Rationale: Breaks down work for planning and control.
Q19: Project exclusions are part of:
A: Scope Statement
Rationale: Clarifies what is not included.
Q20: “Requirements traceability matrix” helps ensure:
A: Requirements are tracked through project life
Rationale: Ensures work aligns with original objectives.
practice exam 2026
, 4|Page
21–30: Schedule & Time Management
Q21: The first scheduling step is:
A: Define Activities
Rationale: Break down WBS work into schedule tasks.
Q22: Sequence activities output is:
A: Network Diagram
Rationale: Shows logical order of work.
Q23: Critical path determines:
A: Longest path and shortest project duration
Rationale: Tasks on critical path have zero float.
Q24: Fast-tracking means:
A: Performing activities in parallel
Rationale: Shortens schedule but increases risk.
Q25: Crashing a schedule increases:
A: Cost
Rationale: Adds resources to reduce duration.
Q26: A Gantt chart is primarily used to:
A: Visualize schedule over time
Rationale: Helps track start/end dates of tasks.
Q27: Free float refers to:
A: Delay allowed without affecting successor tasks
Rationale: Limited to individual activity.