This document contains CDFM Module 4 exam questions with fully verified correct answers, designed to support preparation for the Certified Defense Financial Manager certification. It focuses on advanced defense financial management concepts, including audit readiness, fiscal law application, internal controls, performanceFIAR, and financial analysis, making it suitable for targeted review and exam readiness.

Show more Read less
Institution
CDFM
Course
CDFM










Whoops! We can’t load your doc right now. Try again or contact support.

Written for

Institution
CDFM
Course
CDFM

Document information

Uploaded on
January 17, 2026
Number of pages
21
Written in
2025/2026
Type
Exam (elaborations)
Contains
Questions & answers

Content preview

CDFM Module 4 Exam questions with
correct answers
What |are |Joint |Acquisition |Programs? |- |VERIFIED |ANSWER✔✔-Joint |Acquisition |Programs |is |any
|acqusition |system, |subsystem, |component, |or |technology |program |with |astrategy |that |includes

|funding |by |more |than |one |DoD |component |during |any |phase |of |a |system's |life |cycle.




Who |decides |to |place |programs |under |joint |acquisition |management? |- |VERIFIED |ANSWER✔✔-The
|MDA |decides |whether |to |place |programs |under |joint |management |and |designates |the |lead |executive

|DoD |component.




What |law |requires |an |analysis |of |potential |opportunities |of |international |cooperation? |- |VERIFIED
|ANSWER✔✔-10 |USC |2350a(e) |requires |international |cooperation |consideration |in |the |initial

|aquisition |strategy |for |a |program.




When |international |programs |may |be |established |in |the |defense |acqusition |program |- |VERIFIED
|ANSWER✔✔-Decision |to |include |international |partners |needs |to |be |included |during |development |of

|the |initial |capabilities |document |but |no |early |than |the |material |and |solution |analysis |phase.




When |is |Earned |Value |Management |(EVM) |implemented |- |VERIFIED |ANSWER✔✔-EVM |is |part |of
|program |management |. |It |ensures |that |cost |, |schedule |and |technical |aspects |of |the |contract |are |truly

|integrated.




In |what |type |of |contracts |EVM |is |required |- |VERIFIED |ANSWER✔✔-EVM |is |required |on |Cost, |and/or
|Incentive |contracts |valued |at |greater |than |$20M.




What |is |EVM? |- |VERIFIED |ANSWER✔✔-Earned |Value |Management |is |a |tool |that

1. |Relates |the |scope |of |the |work |to |its |associated |budgets |and |schedule.

2. |Measures |the |work |progress |in |objective |terms

3. |States |that |value |of |the |work |completed |in |dollars |and |other |measurable |units.

,What |are |EVM |techniques? |- |VERIFIED |ANSWER✔✔-Correlate |the |budgeted |cost |of |worked |scheduled
|with |the |budget |cost |of |work |performed |(BCWP)



1. |0/100 |Earned |Value |Technique

2. |Percent |Start/Percent |Finish |EV |Technique |(50/50) |(25/75) |(80/20)

3. |Percent |Complete

4. |Units |Completed

5. |Equivalent |Units



Describe |the |Percent |Start/Percent |Finish |EV |Technique |- |VERIFIED |ANSWER✔✔-Is |an |objective
|earned |value |technique |tied |to |the |start |and |completion |of |a |work |package |task, |often |referred |to |%

|assigned |to |the |start |and |finish |milestone |such |as |(50/50...)



Thsi |technique |tends |to |overstate |performance |in |the |first |half |of |the |period |of |performance |and
|uderstate |performance |in |the |last |half.




What |is |the |most |important |step |in |EVM |system? |- |VERIFIED |ANSWER✔✔-Is |the |establishment |of |the
|Performance |Measurement |Baseline |(PMB)or |the |Budgeted |Cost |of |Work |Schedule |(BCWS)




What |is |the |PMB |in |and |EVM? |- |VERIFIED |ANSWER✔✔-The |PMB |includes |the |undistributed |budget,
|all |summary |level |planning |package |budgets, |and |all |control |account |budgets. |It |does |not |include

|management |reserve.




What |is |the |final |step |of |the |PMB? |- |VERIFIED |ANSWER✔✔-Is |to |classify |work, |to |allocate |the |budget
|and |to |time |phase |the |control |account |work |package |budgets. |This |last |phase |is |calculate |BWCS




How |do |we |classify |work |packages |in |EVM? |- |VERIFIED |ANSWER✔✔-in |3 |categories, |Discrete,
|apportioned |effort, |and |level |of |effort.




Describe |the |realignment |of |the |PMB |- |VERIFIED |ANSWER✔✔-Rebaselining, |Replanning, |and
|Reprogramming




What |is |Reprogramming? |- |VERIFIED |ANSWER✔✔-Reprogramming |is |a |comprehensive |realignment |of
|the |remaining |performance |measurement |baseline |that |results |in |a |total |budget |and/or |total

, |schedule |that |exceeds |the |contractual |requirements. |It |is |the |process |that |results |in |an |Over-Target
|Baseline |or |OTB |and |an |Over-Target |Schedule |OTS.




Schedule |Performance |Index |(SPI) |formula |- |VERIFIED |ANSWER✔✔-SPI=BCWP/BCWS



Estimate |at |Completion |(EAC) |formula |- |VERIFIED |ANSWER✔✔-EAC=ACWP+[(BAC-
BCWP)/(Performance |Factor)]



EAC |Compsite |formula |- |VERIFIED |ANSWER✔✔-ACWPcum+[(BAC-BCWPcum)/(CPIcum*SPIcum)]

Upper |Value |(worst |case)



EVM |Terminology |- |VERIFIED |ANSWER✔✔-EAC=Estimate |at |Completion

BAC=Budget |at |Completion(current)

BCWS=Budget |Cost |of |Work |Scheduled |(current)

BWCP=Budget |Cost |of |Work |Performed |(earned |value)

ACWP=Actual |Cost |of |Work |Performed



What |is |the |Contractor |Cost |and |Software |Data |Reporting |(CSDR) |- |VERIFIED |ANSWER✔✔-The |CSDR
|system |involves |two |formal |contractor |reports, |the |COntractor |Cost |Data |Report |(CCDR) |and |the

|Software |Resources |Data |Report |(SRDR)




What |is |Contract |Performance |Report |(CPR) |- |VERIFIED |ANSWER✔✔-The |PM |should |obtain |from |the
|contractor |a |CPR |(DD |form |2734) |on |all |contracts |the |meet |or |exceed |EVMS |dollar |thresholds |and

|require |EVMS |compliance. |The |CPR |provides |contract |cost |and |schedule |performance |for |program

|mangement.




What |is |Contract |Funds |Status |Report |(CFSR) |- |VERIFIED |ANSWER✔✔-(DD |1586) |has |no |specific
|application |thresholds |but |PMs |should |evaluate |contracts |of |less |than |$1.3M. |FFP |contracts |should

|not |apply |the |CFSR |unless |unusual |circumnstances |dictate |funding |visibility.




What |is |Government |Contract |Quality |Assurance |(GCQA) |- |VERIFIED |ANSWER✔✔-DCMA |Q&A
|personnel |conducts |quality |assurance |as |identified |in |contract |administration |delegations |by |the |KO.

Get to know the seller

Seller avatar
Reputation scores are based on the amount of documents a seller has sold for a fee and the reviews they have received for those documents. There are three levels: Bronze, Silver and Gold. The better the reputation, the more your can rely on the quality of the sellers work.
TUTOROUINE Teachme2-tutor
View profile
Follow You need to be logged in order to follow users or courses
Sold
19
Member since
9 months
Number of followers
0
Documents
1387
Last sold
4 days ago
pure testbanks

Welcome to Smart Study Hub, your go-to destination for high-quality test banks, study guides, and exam solutions. Whether you're preparing for a tough exam or looking for reliable study resources, we've got you covered! ✅ Verified & High-Quality Content ✅ Comprehensive Test Banks & Solutions ✅ Instant Download for Quick Access ✅ Designed to Help You Succeed Study smarter, not harder! Get the best test banks today !

3.3

3 reviews

5
0
4
1
3
2
2
0
1
0

Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their tests and reviewed by others who've used these notes.

Didn't get what you expected? Choose another document

No worries! You can instantly pick a different document that better fits what you're looking for.

Pay as you like, start learning right away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and aced it. It really can be that simple.”

Alisha Student

Frequently asked questions