What component of the project management plan
includes the applicable industry standards and codes the
project is required to follow? - CORRECT ANSWERS
✅Quality Management Plan.
What is a general management technique used to
determine whether particular work can best be
accomplished by the project team or should be purchased
from outside sources? - CORRECT ANSWERS ✅Make
or Buy Analysis.
What ensures that both the seller's and buyer's
performance meets procurement requirements according
to the terms of the legal agreement? - CORRECT
ANSWERS ✅Control Procurements.
What process determines whether to acquire outside
support, and if so, what to acquire, how to acquire it, how
much is needed, and when to acquire it? - CORRECT
ANSWERS ✅Plan Procurement Management.
What type of meeting brings all of the potential vendors
together to discuss the statement of work and the
(Daniels) Exam Question & Answers
2026
What component of the project management plan
includes the applicable industry standards and codes the
project is required to follow? - CORRECT ANSWERS
✅Quality Management Plan.
What is a general management technique used to
determine whether particular work can best be
accomplished by the project team or should be purchased
from outside sources? - CORRECT ANSWERS ✅Make
or Buy Analysis.
What ensures that both the seller's and buyer's
performance meets procurement requirements according
to the terms of the legal agreement? - CORRECT
ANSWERS ✅Control Procurements.
What process determines whether to acquire outside
support, and if so, what to acquire, how to acquire it, how
much is needed, and when to acquire it? - CORRECT
ANSWERS ✅Plan Procurement Management.
What type of meeting brings all of the potential vendors
together to discuss the statement of work and the