Answers |Well Elaborated Solutions|
The SWPPP will contain the following (3) - ANSWER -1. Erosion and sediment
control bet management practices
2. A site specific sequence of construction activiites
3. site maps
Once a site has experienced a rain event of measurable quantity you must identify
- ANSWER -Deficit and fialed BMP's and repair
The document that contains the permit number is - ANSWER -The permit
authorization letter
The portion of the the SWPPP that specifies the content of the SWPPP is -
ANSWER -The table of contents
The document in the SWPPP that certifies the GC's commitment to compliance
with the SWPPP - ANSWER -The SWPPP certification letter
The certifactions letter that identifies the name and contact information of
subcontractors on the site is - ANSWER -The subcontractors certification form
The documents that reveal the total area of disturbance are - ANSWER -The site
maps
, The document completed by the project SWPPP inspector recording site
conditions during the inspection is - ANSWER -The inspection report form
The document that must be completed to report hazardous spill on site is -
ANSWER -The spill report form
The document that verifies that weekly management meetings have been
conducted is - ANSWER -The weekly meeting form
The document delegating responsibility of inspections to another is - ANSWER -
The delegation letter
The document that must be completed when final stabilization is complete is -
ANSWER -The NOT
Scheduling - ANSWER -Aids in protecting the site by timing construction
activities
Factors to consider when creating your schedule include - ANSWER -Account for
the time it takes to install or implement BMP's between each phase of construction
When installing perimeter BMP controls - ANSWER -Note to locations and dates
for installation on site map
Stormwater issues are usually discussed during the pre-con meeting include -
ANSWER -SWPPP BMP's and construction schedule