100% satisfaction guarantee Immediately available after payment Both online and in PDF No strings attached 4.6 TrustPilot
logo-home
Exam (elaborations)

Pre-Assessment Part 1 2026 – Real Exam Questions & Answers

Rating
-
Sold
-
Pages
5
Grade
A+
Uploaded on
13-01-2026
Written in
2025/2026

Prepare for Pre-Assessment Part 1 with this 2026 real exam questions and answers guide. Includes detailed explanations, key concepts, and practice questions to boost your score.

Institution
Pre-Assessment Part 1 –
Course
Pre-Assessment Part 1 –









Whoops! We can’t load your doc right now. Try again or contact support.

Written for

Institution
Pre-Assessment Part 1 –
Course
Pre-Assessment Part 1 –

Document information

Uploaded on
January 13, 2026
Number of pages
5
Written in
2025/2026
Type
Exam (elaborations)
Contains
Questions & answers

Subjects

Content preview

Pre-Assessment Part 1 – Questions & Answers
2026 REAL EXAM!!!




When is a quality audit implemented? - ANSWER ✔✨---Quality Assurance



In which organizational structure is a project manager often referred to as project coordinator or
expeditor? - ANSWER ✔✨---Weak matrix



A user approaches you with a change request that you evaluate and find necessary, even though the
change will result in a large impact to scope. What is your next step? - ANSWER ✔✨---Determine
whether there's an alternative solution that would have less impact on the scope, and discuss the trade-
off with the stakeholder.



Who makes "go/no-go" decisions during phase-gate review? - ANSWER ✔✨---Program governance
board



Larry, your company's CIO, isn't the project sponsor, but he is a key stakeholder, and has demanded that
you add extra website features. How will you handle Larry's request for implementation of the
additional features? - ANSWER ✔✨---Complete and submit a change request form



Which of the following project management process groups utilizes the most project time? -
ANSWER ✔✨---Executing

, You have to describe ownership of project deliverables and authorize someone for their maintenance
and upkeep. Which of the following planswer will you use to accomplish the above task? -
ANSWER ✔✨---Transwerition Plan



You and your team are working on your project's executing process group. There are several actions that
occur during executing processes, including managing project quality, managing risks, preparing
performance reports and information, and more. Which of the following actions does not start in
earnest during this phase? - ANSWER ✔✨---Approving corrective actions



You have a "dream-team" list of people you want on your team, but you're worried that other project
managers may want these same people. What's the best way to approach Brett regarding the
assignment of people to your project? - ANSWER ✔✨---Schedule a meeting with Brett to discuss
resources. Explain your project deliverables and the skill sets you need.



All of the following describe types of project endings except for which one? - ANSWER ✔✨---
Attrition



Tom works as a project manager for BlueWell, Inc. He's determining which risks can affect his project.
Which of the following inputs of the "identify risks" process is useful in doing so and provides a
quantitative assessment of likely cost to complete scheduled activities? - ANSWER ✔✨---Activity
Cost Estimates



You have $400,000 for the budget at completion (BAC). The estimate at completion (EAC) is $200,000.
What is the variance at completion (VAC)? - ANSWER ✔✨---$200,000



Which of the following tools lists all project tasks on the vertical axis with units of time on the horizontal
axis? - ANSWER ✔✨---Gantt Chart



Which of the following documents will you prepare at last during scope definition? - ANSWER ✔✨-
--Work breakdown structure (WBS)



While creating a new project, which of the following contains final project acceptance criteria? -
ANSWER ✔✨---Project Scope Document

Get to know the seller

Seller avatar
Reputation scores are based on the amount of documents a seller has sold for a fee and the reviews they have received for those documents. There are three levels: Bronze, Silver and Gold. The better the reputation, the more your can rely on the quality of the sellers work.
TUTORWILLIAM NURSING
View profile
Follow You need to be logged in order to follow users or courses
Sold
138
Member since
2 year
Number of followers
55
Documents
3409
Last sold
1 week ago
TUTOR WILLIAM

4.8

75 reviews

5
67
4
4
3
1
2
1
1
2

Recently viewed by you

Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their tests and reviewed by others who've used these notes.

Didn't get what you expected? Choose another document

No worries! You can instantly pick a different document that better fits what you're looking for.

Pay as you like, start learning right away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and aced it. It really can be that simple.”

Alisha Student

Frequently asked questions