✔✔What is the delivery method whereby the owner contracts with a single entity? -
✔✔The design build
✔✔Who comprises the DB team? - ✔✔General contractor, subcontractor and a design
professional.
✔✔In the DB scenario, who do the design professionals work for? - ✔✔The contractor
✔✔Construction overlaps with design in which delivery process? - ✔✔Design Build
✔✔What is the delivery method in which the construction manager contracts to deliver a
project within a guaranteed maximum price? - ✔✔CMAR - Construction manager at risk
✔✔What is a way to organize project teams to work in a more creative and productive
manner - integrating all aspects of the design and construction process into a single
team effort? - ✔✔IDP - Integrated project delivery
✔✔What uses a three pronged platform: owner, design professionals, and contractors?
- ✔✔IDP - Integrated project delivery
✔✔Who is the core group that manages the IPD process? - ✔✔Owner, design pro and
the contractor
✔✔95. When does contractor mobilization and materials purchasing occur? - ✔✔the
beginning of the project
✔✔96. The planning and scheduling of construction begins
___________________________. - ✔✔Once the owners and contractors agree on the
plan
✔✔97. True or False: The owner can terminate a contract without cause. - ✔✔True
✔✔98. During construction, whose role includes inspection and observation of the work;
ensuring that the work complies with the contract documents? - ✔✔Architect
✔✔99. Whose role is it to review submittals, interpret the contract documents, and
modify the contract documents as required? - ✔✔Architect
✔✔100. Who coordinates construction activities and is in charge of the construction
site? - ✔✔The CM
, ✔✔101. Whose primary role during the construction phase is the complete the work? -
✔✔The GC and subcontractor
✔✔102. Who is responsible for obtaining permits? - ✔✔The GC and subcontractor
✔✔103. Who is responsible for arranging required tests? - ✔✔The GC and
subcontractor
✔✔104. Who is responsible for maintaining record documents? - ✔✔The GC and
subcontractor
✔✔105. Who is responsible for preparing submittals? - ✔✔The GC and subcontractor
✔✔106. Who is responsible for maintaining a clean and safe work environment? -
✔✔The GC and subcontractor
✔✔107. Who is responsible for correcting any work rejected by the owner's
representative? - ✔✔The GC and subcontractor
✔✔108. List the three types of contracts: - ✔✔Stipulated sum, cost plus fee, unit price
✔✔109. What type of contract is the result of negotiations between the owner and
contractor - ✔✔Stipulated sum
✔✔Most low-bid contracts are ___________ contracts. - ✔✔Stipulated sum
✔✔What type of contract has a shared savings clause or incentives for early
completion? - ✔✔Cost plus fee
✔✔112. This form of contract often leads to value engineering that can generate
savings during the construction phase of the building. - ✔✔Cost plus fee
✔✔113. What type of contract is used when the actual scope of work cannot be
determined at the time of the bid? - ✔✔Unit price
✔✔114. What is the key to obtaining effective bids? - ✔✔Unit price
✔✔115. List the eight commonly required forms during construction administration. -
✔✔notice to proceed, meeting minutes, request for information, field order, proposal
request, change order request, change order, punch list